Daikin RXYQ72PYDN Installation Manual page 21

Vrv iii system air conditioner
Hide thumbs Also See for RXYQ72PYDN:
Table of Contents

Advertisement

In case of cooling mode
(7) Push the TEST button (BS4) once within 5 minutes after procedure
(5) (*4) and close the all front panels (*5).
After that, open the valve A immediately (See figure 31) (*6) and
watch the remote controller display of indoor unit.
(8) If the remote controller display shows "PE" code (*7), ready to close
the valve A.
And go to procedure (9).
If the remote controller display shows other code, close the valve A
immediately and refer to [Remote controller cooling mode malfunc-
tion code]
Beware the fan running when open the front panel.
The fan may continue rotation after the system stop the operation.
(9) When the compressor stop working (the fan may continue rotation.),
close the valve A immediately (*8).
And check the LED displays are as below and the remote controller
display shows "P9" code.
H1P H2P H3P H4P H5P H6P H7P
i
j
j
i
i
After checking, push the MODE button (BS1) once and the charging
is complete.
In case of heating mode
(7) Push the TEST button (BS4) once within 5 minutes after procedure
(5) (*4) and close the all front panels.
After that, open the valve A immediately (See figure 31) (*6) and
check the charged amount by meauring device.
During operation, if the remote controller display shows "P2" or "P8"
code, close the valve A immediately and refer to [Remote controller
heating mode malfunction code].
Beware the fan running when open the front panel.
The fan may continue rotation after the system stop the operation.
(8) When the required amount of refrigerant is charged, close the valve
A (See figure 30) (*8) and push the RETURN button (BS3) once. And
then go to procedure (9).
(9) Push the MODE button (BS1) once, and the charging is complete.
Notes (*1)~(*9)
(*1) Lead the refrigerant charge hose etc from the pipe intake.
All front panels must be closed at the procedure (7).
(*2) • If you perform the refrigerant charging operation within the refrig-
erant system that have the power off unit, the operation cannot fin-
ish properly.
Check the number of outside and indoor units that is powered.
For checking, see [How to check how many units are connected]
in chapter 11-1.
• To energize the crankcase heater, make sure to turn on for
6 hours before starting operation.
(*3) It takes about 2~10 minutes for getting stability of refrigerant state.
If the additional refrigerant is little and operation is started before
getting stability, the system can not judge the charging amount pre-
cisely and it cause over charge.
(*4) If the TEST button (BS4) is not pushed within 5 minutes, "P2" code
will displayed in the remote controller. In this case, refer [Remote
controller cooling (or heating) mode malfunction code].
(*5) If the front panel is opened during the operation, the system cannot
operate properly.
(*6) If you leave the system without connecting the refrigerant tank or
opening the valve A for 30 minutes or more, the system stop oper-
ation and "P2" code are displayed in remote controller.
In this case, refer [Remote controller cooling (or heating) mode mal-
function code].
(*7) Depending on the situation of operation such as the charging
amount is little, the "PE" code may not be displayed and the "P9"
code may be displayed.
(*8) Always close the valve A and take the tank off.
The refrigerant charge port of this unit have electric expansion valve
and the valve are closed when charging is finished. However, the
valve will opened when ather operation (Check operation, nomal
operation, etc.). If you leave the tank connected, the refrigerant will
charged and it cause over charge.
English
i
i
[Remote controller cooling mode malfunction code]
Code
The work contents
PE
Charging is almost finished. Ready to close the valve A.
The refrigerant tank is empty. Close the valve A and replace
empty tank to the new tank. After changing the tank, open the
PA
valve A again.
PH
Beware the fan running. The outside unit does not
stop operation.
Close the valve A immediately, and restart the operation from
P8
procedure (3).
Operation is interrupted. Close the
valve A immedeately and check the
below items.
• Check if gas pipe or liquid pipe
shutoff valve is opened.
P2
• Check the refrigerant tank is con-
nected and the valve A was opend.
• Check if the air inlet and outlet of
the indoor unit are not closed by
an obstruction.
Operation is stoped abnormally. Close
the valve A immediately. Confirm the mal-
function code and correct the abnormality
following the [Remote controller displays
malfunction code] in chapter 11-2-2.
Charging is finished. Close the valve A and take the refriger-
P9
ant tank off.
[Remote controller heating mode malfunction code]
Code
The work contents
Close the valve A immediately and push the TEST button (BS4)
P8
once. And restart from procedure (7) of "In case of heating mode".
Operation is interrupted. Close the valve A immedeately and
check the below items.
• Check if gas pipe or liquid pipe shutoff valve is opened.
P2
• Check the refrigerant tank is connected and the valve A
was opend.
• Check if the air inlet and outlet of the indoor unit are not
closed by an obstruction.
6.
After completing the additional refrigerant charging, record the charging
amount on the accessory "REQUEST FOR THE INDICATON" label
(Installation records) and adhere it to the back side of the front panel.
Also, record the factory charged refrigerant amount, additional refriger-
ant amount in the field and total refrigerant amount of the system to
"ADDITIONAL REF. CHARGE" label and adhere in the proximity of the
refrigerant charge port.
About "ADDITIONAL REF. CHARGE" label, refer to [Important informa-
tion regarding the refrigerant used] in "1-2 Special notice of product".
11-2-2 Procedure of check operation
• Check operation perform the following work. Do the check operation
following below.
Otherwise, malfunction code "U3" will be displayed in the remote
controller and nomal operation can not be carried out.
Check of shutoff valve opening
Check of miswiring
Judgment of piping length
Check of refrigerant overcharge
NOTE
• Check operation can not carried out at outdoor temp. less than 23°F.
Perform the check operation at day or time that outdoor temp. is 23°F
or more.
[Check Operation Procedure]
(1) Close the EL. COMPO. BOX lid and all front panels except as the
side of the EL. COMPO. BOX and turn on the power to the outside
unit and all connected BS, indoor units. (Be sure to turn the power on
at least 6 hours before operation in order to have power running to
the crank case heater.)
(2) Make the onsite settings as needed using the push button (BS1-
BS5) on the outside unit PC-board (A1P) with the power on. (See
"12 Onsite Settings")
After correcting the
abnormality, restart
the operation from
procedure (3).
17

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents