All steps in previous chapters should be understood and carried out before proceeding.

PREPARING SYSTEM FOR OPERATION

Be sure that electrical power is unplugged, valve on C02 cylinder is closed, valve on water
supply line is closed, and release pressure of C02 gas and water from carbonator tank.

PREPARING AND STARTING REFRIGERATION UNIT

1. TOPPER refrigeration is pre-set at factory and ready to operate.
2. Remove cover.
3. Fill water bath with clean water until water runs out of condensate drain outlet, (S-
717).
4. Open water inlet supply line.
5. Plug TOPPER power cord into electrical receptacle box, turn power switch to the "ON"
position. Make sure compressor, condenser fan motor, agitator motor start. The process
of cooling the water bath will now commence. With ambient and water temperature of 75
degree "F" initial pull down or formation of complete ice bank will take approximately 4.5 -
5 hrs. When full ice bank has been formed, compressor and condenser fan motor will
stop. Agitator will continue to operate, circulating water in water bath.

PURGE DISPENSING VALVES

Dispense water from dispensing valves until all air is purged from soda water and non-
carbonated water lines.
ACTIVATE HIGH-PRESSURE C02 SYSTEM
1. Open valve on the C02 cylinder. Be sure to open valve completely or until valve is
back seated.
2. Turn high-pressure C02 regulator screw clockwise until the pressure is 70 to 75 psi,
Carbonated units only.