SECTION XIII- Check-Out Procedures

NOTICE
Perform the following check-out proce-
dures as outlined and check off items as
completed. When procedures are com-
pleted, the installer should complete the
installation record on page 59.
Check-out Procedures
Both inner and outer tanks filled with
water.
Water chemistry checked and verified
as outlined on page 49.
The automatic air vent on the unit and
any place within the system are open
one full turn.
Air is purged from the heating zones
and primary system.
Domestic piping is purged of air and
has been checked for leaks.
Burner has been confirmed as properly
configured for Propane application. (If
applicable).
Thermostat circuit wiring checked and
verify that no voltage is present at the
Room Thermostat Snap-set as outlined
on page 52.
Operating Instructions on page 54 were
followed during start-up.
Combustion levels and flame pattern
verified as outlined on page 55.
Measure the rate of input on Natural
Gas as outlined on page 55.
Check the incoming gas pressure to
ensure a minimum pressure of 5"w.c
during flow conditions to all appliances
and a maximum pressure of 13"w.c
during non-flow conditions for Natural
and Propane.
Primary and Secondary Thermostat
properly set as shown in Figure 38 and
39 page 56.
The thermostatic mixing valve adjusted
to the desired domestic hot outlet tem-
perature.
Adjusted balancing valves and system
limit controls to provide design temper-
atures to the primary space heating sys-
tem.
In multiple zone applications, adjusted
for correct flow of primary heating
water to each zone.
Check and verify room thermostats
functions properly and the thermostats
heat anticipator (if used) was properly
set.
Observed several operating cycles for
proper operation of the PERFOR-
MANCE and the system.
Set the room thermostat(s) to the
desired room temperature.
Reviewed all instructions shipped with
the PERFORMANCE with the home-
owner or maintenance personnel.
Complete the Installation Record on
page 59.
Ensure all manuals and other documen-
tation are returned to the Installation
envelope and given to the owner for
safekeeping.
58

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents