COMMERCIAL GAS

Prepare boiler location

Installations must comply with:
Local, state, provincial, and national codes, laws, regulations and
ordinances.
National Fuel Gas Code, ANSI Z223.1 – latest edition.
Standard for Controls and Safety Devices for Automatically Fired
Boilers, ANSI/ASME CSD-1, when required.
National Electrical Code.
For Canada only: B149.1 or B149.2 Installation Code, CSA C22.1
Canadian Electrical Code Part 1 and any local codes.
The Ultra boiler gas manifold and controls met safe
lighting and other performance criteria when boiler
underwent tests specified in ANSI Z21.13 — latest edi-
tion.

Before locating the boiler, check:

1.
Check for nearby connection to:
System water piping
Venting connections
Gas supply piping
Electrical power
Location of drain for condensate
2.
Check area around boiler. Remove any combustible materials,
gasoline and other flammable liquids.
Failure to keep boiler area clear and free of combustible
materials, gasoline and other flammable liquids and
vapors can result in severe personal injury, death or
substantial property damage.
3.
The Ultra boiler must be installed so that gas control system com-
ponents are protected from dripping or spraying water or rain
during operation or service.
4.
If new boiler will replace existing boiler, check for and correct
system problems, such as:
System leaks causing oxygen corrosion or heat exchanger cracks
from hard water deposits.
Incorrectly-sized expansion tank.
Lack of freeze protection in boiler water causing system and
boiler to freeze and leak.

Provide clearances:

Clearances from combustible materials
1.
Hot water pipes — at least ½" from combustible materials.
2.
Vent pipe — at least
" from combustible materials.
3.
See
Figure 1 for other clearance minimums.
Clearances for service access
1.
See
Figure 1 for recommended service clearances. If you do not
provide minimum clearances shown, it might not be possible to
service the boiler without removing it from the space.
6
-
FIRED WATER BOILER
— Boiler Manual
Clearances
Openings in combustible floors, walls, ceilings or
roofs must be
3
" larger in diameter than the vent pipe
8
and must be lined with steel thimbles and designed for
fire stopping as required by applicable codes.
Provide air openings for combustion air and/
or ventilation of the room as specified in this
manual and as required by applicable codes.
0
0
0
12
20
20
0
0
1
24
2
0
0
3
**
NA
16
1
NA
2
Part number 550-100-086/0809

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ultra-550Ultra-750

Table of Contents