COMMERCIAL GAS
Install condensate components
Connect condensate trap
1.
See
Figure 49.
2.
Remove the protector cap from the bottom of the PVC tee at the
heat exchanger condensate connection (location 2).
3.
Slide a hose clamp over each end of the condensate trap line.
4.
Slide the ends of the line onto the bottom of the PVC tee at the
heat exchanger condensate connection (location 2) and onto the
PVC coupling on the right (location 1).
5.
Slide the hose clamps into position and tighten securely.
Connect condensate line
1.
Connect condensate drain tubing to the 1" PVC condensate tee and
run to floor drain or condensate pump (see Figure 50). Use 1" PVC
or CPVC pipe; or install a hose barb fitting and connect tubing.
Use materials approved by the authority having jurisdic-
tion. In the absence of other authority, PVC and CPVC
pipe must comply with ASTM D1785, F441 or D2665.
Cement and primer must comply with ASTM D2564
or F493. For Canada, use CSA or ULC certified PVC or
CPVC pipe, fittings and cement.
2.
Leave the top of the 1" tee OPEN. This is needed as a vacuum
break.
3.
When installing a condensate pump, select one approved for use
with condensing boilers and furnaces. The pump should have an
overflow switch to prevent property damage from condensate
spillage. See Figure 48 for required flow capacity.
4.
When sizing condensate pumps, make sure to include the total
load of all Ultra boilers connected to it.
The condensate line must remain unobstructed, allow-
ing free flow of condensate. If condensate is allowed to
freeze in the line or if the line is obstructed in any other
manor, condensate can exit from the boiler tee, resulting
in potential water damage to property.
Condensate from the Ultra boiler will be slightly acidic
(typically with a pH from 3.2 to 4.5). Install a neutralizing
filter if required by local codes. See Replacement parts
section at the end of this manual for the Weil-McLain
kit.
Condensate pump capacity, GPH
Ultra-550
14
48
-
FIRED WATER BOILER
Ultra-750
20
— Boiler Manual
(continued)
Condensate trap installed (shown with
inlet air silencer hidden)
2
Condensate pump (by others), typical
For a condensate pump equipped with an
overflow switch, the switch can be connected
to the external manual reset or automatic
reset limit terminals of the U-Control. This
would shut down the boiler in the event of a
condensate overflow. See the wiring diagram
for location of the wiring terminals.
1
Part number 550-100-086/0809

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ultra-550Ultra-750

Table of Contents