Testing the installation

Refer to the programme guide for details of how to select programmes.
1. Turn on the water supply and check for leaks from fill hoses.
2. Switch on the electricity supply.
3. Select a spin programme and then press the MARCHA/PARADA button to
start the machine.
Allow the programme to continue for one minute and then switch off the
machine via the MARCHA/PARADA button. This will remove any water
remaining in the machine from factory testing.
4. To check for cold water filling to the machine:
Select a rinse programme and press the MARCHA/PARADA button to start the
machine.
Allow the tumble action to continue until the water has pumped out.
Check that the drain outlet is not leaking or overflowing.
5. Switch off the machine via the MARCHA/PARADA button at the end of the
cycle.
6. Select a spin programme and press the MARCHA/PARADA button to switch
the machine on. If the machine takes longer than one minute to empty check
the drain hoses for kinks.
Installation testing is now complete.