Installation Preparation - American Standard WALK-IN BATH Installation Instructions And Owner's Manual

Walk-in bath
Hide thumbs Also See for WALK-IN BATH:
Table of Contents

Advertisement

1. Check the floor area where the tub is to be installed.
a. Clean area of any debris or trash.
b. Use a 5 or 6-foot level and determine if the floor is level. If the floor is not level,
adjust all leveling feet to perfectly level the tub.
Note: It is important that all leveling feet are completely touching the floor and
level for the door system to work properly.
2. Check to ensure that the drain piping has been "roughed-in" at the proper location. See
specification sheets (installation detail) included in this manual.
3. Ensure that the proper electrical service has been installed at the pump location. See electrical
Requirements in the manual. (See page 7.)