3. SELECTING INSTALLATION SITE

Select an installation site where the following conditions are satisfied and that meets with your customer's approval.
• Where is resistible against weight of BS unit.
• Locations where the wall is not significantly tilted.
• Where sufficient clearance for maintenance and service can be ensured. (Refer to Fig. 1)
• Locations where an inspection hole (Refer to Fig. 2) can be installed to EL. COMPO. BOX side (See Note).
• Where the total piping length involving indoor unit and outside unit is below the allowable piping length.
(See installation manual attached to outside unit.)
Note: The EL. COMPO. BOX mounting surface can be changed.
For information on how to change the mounting surface, refer to "5. BS UNIT INSTALLATION".
Outside unit
side (3 pipes)
A
Fig. 1
BS Unit Name
BSVQ36P
10 or more
BSVQ60P
10 or more (*2)
NOTE
• Study if the installation location is strong enough to hold the weight of the unit, and if necessary reinforce
the area with a beam or other member and then install suspension bolts. Use the suspension bolts to install
the unit. (Refer to "4. PREPARATIONS BEFORE INSTALLATION")
• Install the BS unit and its power supply wiring and transmission wiring at least 40 in. away from televisions
and radios to prevent image distortion and noise in those devices. Noise may still be introduced at this dis-
tance depending on the electromagnetic wave conditions.

4. PREPARATIONS BEFORE INSTALLATION

Refer the figure 3 and install the suspension bolts and hanging brackets.
〈Suspension bolts: For supporting the product〉
• Use M8-M10 suspension bolts.
• When holes are to be made anew, used embedded inserts and embedded foundation bolts. When holes
are already provided, use hole-in-anchors or the like.
Install the BS unit so that its weight can be withstood.
〈Hanging bracket: For supporting the connection pipe〉
• Be sure to support the connection piping around the unit using hanging brackets that are kept within
40 in. of the body side surface. Hanging excessive weight on the BS unit hanging bracket could cause the
unit to fall and injure someone.
5
Indoor unit
side (2 pipes)
B
(in.)
A
B
10 or more (*1)
10 or more (*2)
(in.)
BS unit
proper top
(*1) When using accessory pipes 1)-1, 2 (Refer to 6-5 PIPING
CONNECTION), provide a service space of at least 12 in..
(*2) When using accessory pipes 1)-1, 2 (Refer to 6-5 PIPING
CONNECTION), provide a service space of at least 14 in..
(*3) When using accessory pipes 1)-1, 2 (Refer to 6-5 PIPING
CONNECTION), provide a service space of at least 16 in..
(in.)
EL. COMPO. BOX
Inspection hole
18
Be sure to open this to the
EL. COMPO. BOX side.
Fig. 2
English

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Bsvq60pvju

Table of Contents