Unit Assembly; General; Unit Assembly - All Sizes - Trane CLCH-IM-16A Installation And Maintenance Manual

Climate changer central station air handlers, draw-thru and blow-thru unit sizes 3, 6, 8, 10, 12, 14, 17, 21, 25, 30, 35, 40, 50, 66, 80, and 100
Table of Contents

Advertisement

The T-Series Climate Changer is extremely versatile
and can be assembled in many configurations. Prior
to unit assembly, refer to the correct submittals
and unit tagging for correct placement of
accessory sections. Failure to review the submittal
could result in performance or assembly problems. If
there are any discrepancies, contact your local Trane
representative before proceeding.
IMPORTANT: All shipping support screws on the
face of the sections and sectional subassemblies
must be removed and discarded to permit proper fit-
up and sealing of the surfaces.

General

WARNING
To avoid personal injury or death
keep open flame away from unit
exterior or interior. Do not weld or
use cutting torch on the exterior or
interior of the unit. The unit con-
tains polyurethane insulation. Fail-
ure to keep open flame away from
unit exterior or interior may result
in the production of toxic gas that
could result in death or serious
injury.
CAUTION
The internal sections of this unit
containing electrical components
must not exceed 104
ture. Internal sections of the unit
not containing electrical compo-
nents must not exceed 180
perature. Failure to comply with
temperature requirements may
cause equipment damage.
Units may be mounted on the roof with a roof curb or
pier mount. Refer to submittals for dimensions and
roof openings. Provide clearance around the unit to
allow adequate free air and necessary service
access. Also, allow room for supply and return
16
o
F tempera-
o
F tem-
piping, ductwork, electrical connections, and coil
removal.
The building roof must be able to support the entire
weight of the unit, roof curb and accessories. See
Table 1 thru Table 4 for unit and accessory weights.
q Prepare the roof curb or pier mount and roof
openings before hoisting the unit to the roof.
q Check that the gasketing is intact and provides an
airtight seal with the unit base. Refer to the
applicable roof curb installation manual.
q Complete all ductwork, piping and electrical
connections only after mounting the unit. Refer to
unit submittals.
All T-Series Climate Changer units are identified by a
multiple-character model number that identifies each
section. It is located on the panel on the inside of the
supply fan section access door. Be sure to refer to
the information on the nameplate when ordering
replacement parts or requesting service
Assembly Hardware
T-Series Climate Changers ship with all necessary
assembly hardware and gasket material. This
hardware is packaged in either a clear plastic
envelope or cardboard box and can be found inside
the Fan section, Access section, or Mixing section.
The number of sections to be assembled often
makes it necessary to use more than one section to
ship the material. Please check all sections
thoroughly before contacting your Trane Company
Representative to report missing hardware.

Unit Assembly - All Sizes

Mounting
If a unit arrives in sections, then each section must
be individually hoisted, set on a roof curb or pier
mount and assembled.
The pipe cabinet must also be mounted as an
individual section. Refer to the pipe cabinet assembly
section following for specific instructions.
When mounting the unit on its roof curb or pier mount
make sure that the gasketing between the roof curb
or pier mount and unit base provides an airtight seal.
See Figure 7 and Figure 8 for suggested pier/rail
mounting.