Commissioning
Fuel for the commissioning
For the commissioning, sufficient dry fuel (max. W 20%)
should be stored for approx. 10-24 full operating hours:
PYROTEC
390
PYROTEC
530
PYROTEC
720
PYROTEC
950
PYROTEC
1250
Since the boiler plant will be cold, and residual moisture
will be drawn from the refractory concrete during the
initial operation, the material to be burned for the initial
operation has to be at least air dry. For the first three hours,
the heating-up process should be carried out at low output.
To ensure that the silo extraction system is functioning
properly, only place a minimal amount of fuel in the silo
in case there is a problem. This enables the extraction
system to be cleaned out quickly and the problem to be
identified and corrected.
approx.
5100 lb.
approx.
6600 lb.
approx.
8800 lb.
approx.
11660 lb.
approx.
14960 lb.