Table 2-5 Factory-Integrated Installation Checklist (continued)
Procedure
Allow proper clearance
Cut polystrap bands
Remove cardboard top cap
Remove corrugated wrap
from the pallet
Remove four bolts holding
down the ramps and
remove the ramps
Remove antistatic bag
Check for damage (exterior
and interior)
Position ramps
Roll cabinet off ramp
Unpack the peripheral cabinet
(if ordered)
Unpack other equipment
Remove and dispose of
packaging material
Move cabinet(s) and equipment
to computer room
Move cabinets into final position
Position cabinets next to
each other (approximately
1/2 inch)
Adjust leveling feet
Install anti-tip plates
Inspect cables for proper
installation
Set up CE tool and connect to
Remote RS-232 port on MP
Apply power to cabinet
(Housekeeping)
Check power to BPSs
Log in to MP
Set LAN IP address on MP
Connect customer console
Set up network on customer
console
Verify LAN connection
Verify presence of cells
Power on cabinet (48 V)
72
Installing the Server
In-process
Completed