Execute the Site Plan
To ensure site preparation is complete by the scheduled equipment
delivery date, the customer should arrange for contractors as soon as the
plan has been laid out and computer room requirements are determined.
All major facility changes and primary power and air conditioning
installation should be completed 30 days prior to the scheduled
installation date.
The Hewlett-Packard site preparation specialist may assist in arranging
for the necessary contractors if requested by the customer.
It is the customer's responsibility to ensure their computer system site is
in compliance with all local laws, regulations, and codes for mechanical,
building, and electrical distribution systems prior to system installation.
The Hewlett-Packard site preparation specialist can assist the customer
in determining the local regulations.