Low Voltage Battery Quick Installation Guide 1 General Declaration • Read this quick installation guide carefully before installation to learn about product features and safety precautions. • Only qualified personnel are allowed to install, operate, and maintain the equipment. • Installers should be familiar with local laws and regulations. •...
Low Voltage Battery Quick Installation Guide 4 Installation Instruction Environmental Requirements 1. The recommended ambient temperature is between 15℃ and 35℃. 2. The recommended relative humidity is between 10% and 95%, without condensing. 3. The altitude should be no more than 2000 m. 4.
Page 6
Low Voltage Battery Quick Installation Guide 2. Place the bracket L according to the bottom 4 holes. 3. Use M8 expansion screws to fix the bracket L on the wall with a torque of 15 N·m. 4. The method to install bracket R is the same as that of bracket L. 15 N·m Step 4 Placing the Battery 1.
Low Voltage Battery Quick Installation Guide Floor Standing Step 1 Drilling Holes As described in the wall mounting steps, according to the actual installation, place the positioning paper (Floor Standing Side) against the wall, mark hole position (for bracket A), drill holes, and hammer the sleeves into the holes.
Low Voltage Battery Quick Installation Guide 5 Electrical Connection NOTICE • Before the electrical connection, ensure that all power supplies are disconnected. • It is recommended that a circuit breaker between the inverter and the battery be installed in accordance with local laws and regulations.
Page 11
≤ 6 kW) 1. LB-5D-G2 series supports up to 16 batteries in parallel. 2. When the power of the inverter is less than or equal to 6 kW, batteries can be connected directly to it without a busbar, and the maximum charging or discharging current of the battery system is 100 A. If the current exceeds 100 A, it may cause a risk of fire accident.
Page 12
Low Voltage Battery Quick Installation Guide Parallel Connection with Busbar (Inverter Power > 6 kW) 1. LB-5D-G2 series supports up to 16 batteries in parallel. 2. When the power of inverter exceeds 6 kW, batteries must be connected to it through a busbar.
2. Turn on the power switch and long press the “RESETˮ button for 3s. The battery will be in self-check state and all indicators will flash blue (0.5s gap). Note: • If the battery works with Hoymiles inverters, leave the DIP Switch as default. • If the battery works with non-Hoymiles inverters, please contact Hoymiles. COM IN...
The battery is turned off. 7 EU Declaration of Conformity Hoymiles Power Electronics Inc. hereby declares that Hoymiles Battery (model: LB-5D-G2) is in compliance with the essential requirements and other relevant provisions of directives 2014/30/EU, 2014/35/EU, 2011/65/EU, (EU)2015/863, and EU Battery Regulation (EU)2023/1542.
Page 16
User Manual in the QR code or at www.hoymiles.com/resources/download/ Hoymiles Power Electronics Inc. Add: Floor 6-10, Building 5, 99 Housheng Road, Gongshu District, Hangzhou 310015, P . R. China Tel: +86 571 2805 6101 Email: service@hoymiles.com support@hoymiles.com AP041018 www.hoymiles.com...