Page 1
WE-EF LEUCHTEN Installation and Maintenance Instructions Bollard PSY414 LED PSY424 LED PTY414 LED PTY424 LED Do not open during installation Surge Protection This product is factory-sealed. This product features built-in surge protection circuitry in compliance Refer to the instructions contained with applicable standards.
Page 2
Bollard PSY414 PTY414 14.5 PSY424 PTY424 14.5 IP66/IP67, IK10, Class I, ta = 40°C Weight Accessories: for PSY414 13.3 Planted root – Galvanised steel. for PSY424 16.1 ESV2 for PSY414/424 300-9115 for PTY414 14.0 ESV2 for PTY414/424 300-9115 for PTY424 19.0 ESV2...
Light Source Maintenance Apart from cleaning the product’s exterior surfaces, no special maintenance work is required. Do not use high-pressure cleaners. In case of component failure due to abnormal circumstances or at end of life, replacement must be carried out by a suitably qualified and trained professional. Warning: Do not open luminaire while mains supply is switched on.
Installation The product must be installed and maintained by a suitably qualified professional in compliance with latest building/construction and/or electrical regulations and relevant legislation. Warning: Switch off mains electrical supply prior to installing and connecting the luminaire. Notice: If the luminaire is modified by anybody other than the original manufacturer, then the warranty will no longer be valid and shall become the full responsibility of the modifying person/organisation.
Installation Procedure It is recommended to incorporate the optional planted root to ensure maximum stability. 1) Switch off mains electrical supply. 2) Remove sleeve A from post B. 3) Pull cable through centre-hole and screw 4) Loosen screws O and remove terminal box flange plate E with M12 bolts/nuts to ground.
Page 6
5) Check that rating shown on luminaire label 6) Pull cable D (and second cable for through conforms with mains electrical supply. wiring, if required) through cable gland(s) F and terminate in terminal block G. Tighten 08/18 IP66 cable gland(s) F. PSY424 220-240V/50-60 Hz 114-XXXX...
Page 7
9) Align sleeve A into flange plate E 10) Remove countersunk screws J from head K (good and bad engagement). with Torx 25 tool (supplied by WE-EF). 11) Hold head K under arm. Grab socket L, 12) Place head K over sleeve A and check for connect and tighten with plug M.
Page 8
13) Tighten recessed screws N gradually in 14) Return countersunk screws J into head and alternating sequence (6 Nm) with Torx 30 tool tighten. (supplied by WE-EF).
Installation Instruction 1) Note: It is the responsibility to installer to 2) Please note, ESV4 and ESV6 must be ensure the suitability of the ESV/ESZ planted root for any local or national structural require- In both instances conduit entry can be rotated ments for installation, and that planted root is to match cable routing.
Page 14
5) For ESZ4 please orientate planted root as shown (base plate is parallel to the pathway). cal connections/conduit. For this installation, use 30 mm long M12 bolts for PSY planted root and 35 mm long M10 bolts for MRY planted root. M12 x 30 M10 x 35 7) Place the ESV/ESZ in the form work for con-...
Page 15
9) Pour concrete to desired level depending on requirement of concrete, paver or soil. Ensure (as per luminaire instructions) onto mounting level. Concrete Paver Soil...
Need help?