Polon-Alfa VENTUM PRO LITE Technical Manual

Aspirating smoke detector
Hide thumbs Also See for VENTUM PRO LITE:
Table of Contents

Advertisement

Quick Links

FIRE DETECTION
ASPIRATING SMOKE DETECTOR
VENTUM PRO LITE
_________________________________________________________________________________
Technical manual
IK-E392-001-GB
Edition I

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the VENTUM PRO LITE and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Polon-Alfa VENTUM PRO LITE

  • Page 1 FIRE DETECTION ASPIRATING SMOKE DETECTOR VENTUM PRO LITE _________________________________________________________________________________ Technical manual IK-E392-001-GB Edition I...
  • Page 2: Table Of Contents

    Contents Aspirating smoke detector VENTUM PRO LITE Contents 1 General information ..........................7 Introduction ............................7 Safety notices ............................. 7 1.2.1 Personal injury ........................8 1.2.2 Material and environmental damage ..................8 1.2.3 Other notices ........................... 9 Warranty and limitation of liability ....................... 9 Copyright ............................
  • Page 3 Aspirating smoke detector VENTUM PRO LITE Contents 3.3.4 Ceiling feed-throught ......................42 3.3.5 Air filter and special filter ....................... 44 3.3.6 Air return ..........................48 3.3.7 Silencer ..........................49 3.3.8 Condensate separator ......................50 3.3.9 Detonation prevention device ....................52 4 Technical data ............................
  • Page 4 Contents Aspirating smoke detector VENTUM PRO LITE Energy supply ..........................115 6 Installation ............................120 General information ........................120 Determination of installation location ..................... 121 Installation of device ........................121 Opening the device ........................125 Making settings ..........................126 6.5.1 Setting the response sensitivity (main alarm) ..............
  • Page 5 Aspirating smoke detector VENTUM PRO LITE Contents 6.14 Installation of the pipe system ......................162 6.15 Installation of the aspiration pipe ....................163 6.16 Installation of the aspiration hose ....................163 6.17 Installation of aspiration apertures ....................165 6.18 Installation of the ceiling feed-throught ..................166 6.18.1 Installation of the ceiling feed-throught ................
  • Page 6 Contents Aspirating smoke detector VENTUM PRO LITE Checking the air flow monitoring and fault signal transmission ............. 199 Function test ........................... 201 7.4.1 Preparing for the function test ..................... 201 7.4.2 Performing the function test ....................203 8 Maintenance ............................206 Maintenance intervals ........................
  • Page 7: General Information

    POLON-ALFA S.A. shall not be liable for any damages or losses that might result from failure to comply with this technical manual.
  • Page 8: Personal Injury

    1 | General information Aspirating smoke detector VENTUM PRO LITE 1.2.1 Personal injury DANGER Type and source of hazard ... indicates an immediately dangerous situation that leads to death or serious injury if it is not avoided. WARNING Type and source of hazard ...indicates a possibly dangerous situation that leads to death or serious...
  • Page 9: Other Notices

    This document is subject to technical modifications without prior announcement and makes no claim to completeness. The "delivery and installation conditions" of POLON-ALFA S.A. apply as a matter of principle. Guarantee and liability claims in the case of personal injuries and damage to property cannot be asserted if they are based on one or more of the following causes: ▪...
  • Page 10: Packaging

    1 | General information Aspirating smoke detector VENTUM PRO LITE The technical manual is exclusively intended for the installer and his employees. Reprinting of the technical manual, including excerpts, is not permitted. Reproduction or distribution of the technical manual in any form is only permitted with written authorisation from POLON-ALFA S.A.
  • Page 11: Information For The Operating Company

    Aspirating smoke detector VENTUM PRO LITE 1 | General information Information for the operating company Perform regular visual inspections and function tests to ensure the system remains functional. Such tests are an integral part of the system documentation and must be set out by the installer of the system in accordance with the system parameters.
  • Page 12: Product Description

    You will find the characteristics and application areas in this chapter. Characteristics The VENTUM PRO LITE belongs to the group of tried and tested aspirating smoke detectors of POLON-ALFA S.A. In addition to monitoring rooms and equipment, the device can be used to monitor air conditioning units or ducts.
  • Page 13: Areas Of Application

    PRO LITE-SL) by means of bridges BR1 and BR2: 10 V, 11 V or 12 V Areas of application The VENTUM PRO LITE is used for early fire and very early fire detection in rooms and facilities. Principle Air samples are taken from the monitored area using a pipe system with defined sampling points and supplied to the detector module.
  • Page 14 2 | Product description Aspirating smoke detector VENTUM PRO LITE ▪ ... electromagnetic fields are present. ▪ ... point-type smoke detectors are difficult to access and installation or maintenance is difficult to carry out. ▪ ... the height of the monitoring area is greater than permitted for point- type smoke detectors.
  • Page 15: Image 1 Principle Of Room Monitoring

    Aspirating smoke detector VENTUM PRO LITE 2 | Product description Image 1: Principle of room monitoring 1 Raised floor 2 Pipe system installed in raised floor (partially concealed) 3 Pipe system installed below the ceiling 4 VENTUM PRO LITE Room monitoring with air-...
  • Page 16: Image 2 Principle Of Room Monitoring With Air-Conditioning

    2 | Product description Aspirating smoke detector VENTUM PRO LITE Image 2: Principle of room monitoring with air-conditioning (e.g. air circulation units or air-conditioning ducts) 1 Air-conditioning duct 2 Airflow 3 VENTUM PRO LITE 4 Ventilation grille 5 Air circulation unit...
  • Page 17: Image 3 Principle Of Equipment Monitoring

    2 | Product description Image 3: Principle of equipment monitoring The VENTUM PRO LITE can also be used for very early fire detection in rooms with special air conditioning. High-quality goods and systems can be reliably monitored thanks to the high sensitivity level.
  • Page 18: Technical Description

    ▪ A fan to transport the air samples to the detector module On the VENTUM PRO LITE TWO, one of the two detector modules can be optionally equipped with or without air flow sensor and with or without LOGIC·SENS.
  • Page 19: Function

    Up to four different sensitivity levels can be set on the detector module (see chapter "Sensitivity"). Two monitoring areas can be monitored with a VENTUM PRO LITE TWO (two detector modules). Dual detection dependency and, additionally, a pre- alarm can be achieved by choosing different response sensitivities when monitoring an individual monitoring area.
  • Page 20 Faults caused by temporary ambient fluctuation can be hidden by adjusting a time delay. LOGIC·SENS A switch on the detector module of the VENTUM PRO LITE can be used to activate or deactivate the intelligent signal processor LOGIC·SENS. By means of the intelligent signal processing, LOGIC·SENS enables deceptive phenomena to be overridden and thus contributes to safe operation without false alarms.
  • Page 21: Image 5 Example Of Signal Path Airflow Sensor Fault

    Alarm and fault messages are reset via a connected fire detection control panel. A reset circuit board can be optionally used if, in case of operation of the VENTUM PRO LITE via a fire detection control panel with collective detection lines, alarm and fault messages are reset simultaneously with the resetting of the detection lines.
  • Page 22 20 aspiration apertures can be connected to the VENTUM PRO LITE with one detector module. Two pipe systems can be connected to the VENTUM PRO LITE TWO with two detector modules. The overall pipe system may have a total length of max.
  • Page 23: Structure And Accessory Components

    Aspirating smoke detector VENTUM PRO LITE 3 | Technical description Structure and accessory components 3.2.1 Overview Image 6: Structure an accessory components IK-E392-001-GB...
  • Page 24: Device

    – Pipe connection for air return ▪ Fan (standard or silent) with optimised air supply ▪ LEDs for alarm, fault and operation; additionally with VENTUM PRO LITE TWO: Alarm 2 ▪ Motherboard with interface for diagnostic tool ▪ Membrane cable entries (3x enclosed)
  • Page 25: Image 7 Displays And Connections

    Aspirating smoke detector VENTUM PRO LITE 3 | Technical description ▪ Sensitive detector module according to the principle of optical scattered light detectors with additional air flow monitoring ▪ Front film sheet to display device information Image 7: Displays and connections...
  • Page 26: Detector Box

    3.2.3 External detector boxes can be installed in the pipe system in conjunction with the VENTUM PRO LITE. The detector box can be used in order to ... ▪ ... set up dual detection dependency. ▪ ... be able to localise the branch with smoke in a multi-branch pipe system.
  • Page 27: Image 10 Functional Principle Of Detector Box (Dual Detection Dependency)

    Aspirating smoke detector VENTUM PRO LITE 3 | Technical description Image 10: Functional principle of detector box (dual detection dependency) 1 VENTUM PRO LITE 2 Pipe system 3 Detector box 4 Aspiration aperture IK-E392-001-GB...
  • Page 28: Image 11 Functional Principle Of Detector Box

    3 | Technical description Aspirating smoke detector VENTUM PRO LITE Image 11: Functional principle of detector box (localisation and increase of the response sensitivity) 1 VENTUM PRO LITE 2 Pipe system 3 Detector box 4 Aspiration aperture The detector box consists of the following components: ▪...
  • Page 29: Image 13 Front Film Sheet Of The Detector Box

    Aspirating smoke detector VENTUM PRO LITE 3 | Technical description Image 12: Detector box 1 Detector box 2 Cable glands 8x M20 3 Cable glands 6x M25 4 Front film sheet 5 Pipe connection 6 Membrane cable entries 1x M20 (enclosed with device base pack)
  • Page 30: Diagnostic Tool

    The data is transmitted via a 6-pin ribbon cable which is connected via the plug connector X2 on the basic board of the VENTUM PRO LITE. Diagnostic messages are stored for at least three days in the device in order to allow analysis of short, sporadically occurring faults (e.g.
  • Page 31: Response Indicator

    All stored and current diagnostic data as well as settings made of the VENTUM PRO LITE can be saved in the form of a file or an automatically created log using the diagnostic software. Store and archive every file under another file name for the purpose of later comparison.
  • Page 32: Device Brackets

    3 | Technical description Aspirating smoke detector VENTUM PRO LITE 3.2.6 Device brackets Image 16: Device brackets The VENTUM PRO LITE can be directly mounted on a wall. Additional brackets can be delivered if required (e. B. for fixing to shelf racks). IK-E392-001-GB...
  • Page 33: Pipe System

    Aspirating smoke detector VENTUM PRO LITE 3 | Technical description Pipe system The pipe system serves for extraction of consistent air out of the monitoring areas. IK-E392-001-GB...
  • Page 34: Entire Overview Of Available Pipe Components

    3 | Technical description Aspirating smoke detector VENTUM PRO LITE 3.3.1 Entire overview of available pipe components Image 17: Available pipe system components IK-E392-001-GB...
  • Page 35 Aspirating smoke detector VENTUM PRO LITE 3 | Technical description 1 Special filter type SF-650 2 Condensate separator type KA-DN-25 3 Condensate separator type KA-1-P 4 Detonation protector 5 T-piece 6 Curve 90° 7 Ceiling duct set (3-part) 8 Sleeve 9 Double screw connection 10 90°...
  • Page 36: Air Purge System

    3 | Technical description Aspirating smoke detector VENTUM PRO LITE for refrigerated areas and/or air purge systems Select the components shown for the corresponding application and also use them in combination. 3.3.2 Air purge system NOTE Damage of aspiration reducing film sheets due to purging If air purge systems are used, aspiration reducing film sheets can be damaged or detached in the purging process.
  • Page 37: Image 18 Manual Air Purge System With Metal 3-Way Ball Valve

    Aspirating smoke detector VENTUM PRO LITE 3 | Technical description Image 18: Manual air purge system with metal 3-way ball valve 1 Device 2 Pipe system 3 3-way ball valve (metal) A Compressed air B Air flow for purging IK-E392-001-GB...
  • Page 38: Image 19 Manual Air Purge System With 3-Way Ball Valve Made Of Abs Or Pvc

    3 | Technical description Aspirating smoke detector VENTUM PRO LITE Image 19: Manual air purge system with 3-way ball valve made of ABS or PVC 1 Device 2 Pipe system 3 3-way ball valve (ABS/PVC) A Compressed air B Air flow for purging...
  • Page 39: Sampling Points

    Aspirating smoke detector VENTUM PRO LITE 3 | Technical description 3.3.3 Sampling points Image 20: Aspiration borehole and aspiration reducing film sheet 1 Aspiration reducing film sheet 2 Aspiration pipe (pipe system) 3 Aspiration borehole Ø 10 mm A sampling point is a 10 mm borehole in the aspiration pipe, which is covered with a aspiration reducing film sheet.
  • Page 40: Image 21 Aspiration Aperture, Aspiration-Reducing Film Sheet And Marking Tape

    3 | Technical description Aspirating smoke detector VENTUM PRO LITE 3.3.3.1 Aspiration reducing film sheet and sleeve Image 21: Aspiration aperture, aspiration-reducing film sheet and marking tape 1 Aspiration-reducing film sheet 2 Air sampling pipe (pipe system) 3 Aspiration aperture Ø 25/64" (10 mm)
  • Page 41: Image 22 Aspiration Reduction Clips

    Aspirating smoke detector VENTUM PRO LITE 3 | Technical description NOTE Damage of aspiration reducing film sheets due to purging If air purge systems are used, aspiration reducing film sheets can be damaged or detached in the purging process. ► Use aspiration reducing clips with appropriate aspiration reductions.
  • Page 42: Ceiling Feed-Throught

    3 | Technical description Aspirating smoke detector VENTUM PRO LITE more stable and the cleaning effect is significantly better for pressurisation due to the elastic rubber inserts. 3.3.4 Ceiling feed-throught Image 23: Ceiling feed-throught 1 Ceiling 2 Pipe system 3 T-piece (pipe hood)
  • Page 43: Image 24 Ceiling Feed-Throught For Special Applications

    Aspirating smoke detector VENTUM PRO LITE 3 | Technical description The ceiling duct can be used for suspended ceiling boards up to a thickness of approx. 35 mm. If the length of these capillary hoses is maximum 1 m, project planning applies in accordance with chapter "Project planning".
  • Page 44: Air Filter And Special Filter

    3 | Technical description Aspirating smoke detector VENTUM PRO LITE NOTE Missing monitoring for rupture The capillary hose cannot be monitored for rupture in case of the special application of ceiling feed-throughts in which the aspiration reducing film sheets are upstream in T-pieces (pipe hoods).
  • Page 45: Image 26 Filter Lf-Ve In Multiple Aspiration Branches

    Air filter – type and areas of application The air filter is automatically monitored for dirt (blockage) by the airflow monitoring of the VENTUM PRO LITE. If air filters are soiled, the filter inserts can simply be replaced after opening the filter housing.
  • Page 46: Image 27 Filter Lf-Ve In Auxiliary Branch

    3 | Technical description Aspirating smoke detector VENTUM PRO LITE Instead of an air filter in the main branch, an air filter of the same type can be installed in each descending branch to extend the maintenance intervals. The same project planning specifications as defined in the project planning table apply (see Chapter annex).
  • Page 47: Image 28 Installing Special Filter And Air Filter In Combination

    Aspirating smoke detector VENTUM PRO LITE 3 | Technical description Table 3: Special filter (air filter) – type and areas of application Image 28: Installing special filter and air filter in combination 1 VENTUM PRO LITE 2 Special filter type SF-400 or SF-650...
  • Page 48: Air Return

    2 Device 3 Air return If the VENTUM PRO LITE and pipe system are installed in areas with different air pressure (e.g. P1 and P2), return of the air into the pipe system pressure area is required. The air return can be used for pressure compensation or to prevent air pollution (e.g.
  • Page 49: Silencer

    3.3.7 Silencer Image 31: SD-1-P silencer In monitoring areas where low noise emission of the VENTUM PRO LITE is necessary (e.g. in offices of hospitals), the silencer SD-1-P can help reduce the noise level. IK-E392-001-GB...
  • Page 50: Condensate Separator

    Install the condensate separator at the lowest point of the pipe system upstream of the air filter and the VENTUM PRO LITE to collect the condensate. Condensate separators are used in monitoring areas with: ▪...
  • Page 51: Image 33 Steam Trap Type Ka-1-P

    Aspirating smoke detector VENTUM PRO LITE 3 | Technical description Type KA-1 Image 33: Steam trap type KA-1-P 1 Steam trap 2 Pipe system 3 Air filter (optional) 4 VENTUM PRO LITE The condensate separator can be operated within a temperature range of 0 °C …...
  • Page 52: Detonation Prevention Device

    Detonation protector Due to the additional installation of detonation protectors in the pipe system, the VENTUM PRO LITE can also be used for monitored areas with potentially explosive atmospheres (Ex areas). Detonation protectors are used as protection in Ex areas, as pipe deflagrations or detonations can occur in the event of ignition of vapour/air mixtures or gas/air mixtures.
  • Page 53: Table 4 Explosion Groups For Detonation Protectors

    * Federal Institute for Material Testing Pipe system and earthing Design the pipe system between the VENTUM PRO LITE and the detonation protectors as steel pipes (type R-2525). Aspiration and airflow pipe in the Ex area to be monitored can be either made of plastic or metal.
  • Page 54 3 | Technical description Aspirating smoke detector VENTUM PRO LITE ▪ Conductive paint ▪ Conductive wire mesh ▪ Conductive plastic pipes. Conductive paint must be applied evenly to all parts of the pipe system at a later time on site. Specific thicknesses must not be exceeded. Wire mesh must be braided on site (e.g.
  • Page 55: Technical Data

    Aspirating smoke detector VENTUM PRO LITE 4 | Technical data Technical data You will find the technical data in this chapter. Device VENTUM PRO LITE VENTUM PRO LITE TWO Voltage Supply voltage (Ue) [V] 14 … 30 Nominal supply voltage [V] Current All current consumptions specified refer to an ambient temperature of 20 °C.
  • Page 56 4 | Technical data Aspirating smoke detector VENTUM PRO LITE Protection class IP code in accordance with IP 20 IEC/DIN EN 60529 Impact resistance In accordance with IEC/EN 62262, EN IK 04 50102 Housing Material Plastic (ABS) Colour RAL 9018, Papyrus white...
  • Page 57 Aspirating smoke detector VENTUM PRO LITE 4 | Technical data VENTUM PRO LITE VENTUM PRO LITE TWO Temperature range [°C] –30 … +60 Air humidity Non-condensing [% RH] 10 … 95 Design Radial Fan service life (12 V) [h] 43,500 (at 24 °C)
  • Page 58 4 | Technical data Aspirating smoke detector VENTUM PRO LITE Silent version VENTUM PRO LITE-SL VENTUM PRO LITE TWO- Voltage Supply voltage (Ue) [V] 14 … 30 Nominal supply voltage [V] Current All current consumptions specified refer to an ambient temperature of 20 °C.
  • Page 59 Aspirating smoke detector VENTUM PRO LITE 4 | Technical data Sound pressure level LpA according to EN ISO 3744 from 31 without silencer [db (A)] LpA according to EN ISO 3744 from 23 with silencer [db (A)] depending on project planning and fan voltage...
  • Page 60: Accessories

    4 | Technical data Aspirating smoke detector VENTUM PRO LITE Cable twisted in pairs, shielded or unshielded Cross-section Terminals for max. 1.5 mm² wires Cable glands 5x M20, 2x M25 Conical pipe connections 1x for aspiration pipe 2x for aspiration pipe Ø...
  • Page 61 Aspirating smoke detector VENTUM PRO LITE 4 | Technical data IP rating IP code in accordance with IEC/EN IP54 60529 Impact resistance In accordance with IEC/EN 62262, EN IK04 50102 Housing Material Plastic (ABS) Colour RAL 9018, Papyrus white Temperature range [°C]...
  • Page 62: Response Indicator

    4 | Technical data Aspirating smoke detector VENTUM PRO LITE Response sensitivity Detection unit DM-MB-TMx-x-10 [% light 0.1 … 2.0 obscuration/m] DM-MB-TMx-x-50 [% light 0.5 … 2.0 obscuration/m] Response indicator 4.2.2 Voltage Supply voltage (Ue) [V] 5 … 8 Nominal supply voltage [V DC] Current All current consumptions specified refer to an ambient temperature of 20 °C.
  • Page 63: Pipe System

    Aspirating smoke detector VENTUM PRO LITE 4 | Technical data Connections Terminal connections [mm²] max. 1.5 mm Fire alarm cable shielded (e.g. type J-Y(ST)Y) Pipe system VENTUM PRO LITE VENTUM PRO LITE TWO VENTUM PRO LITE-SL VENTUM PRO LITE TWO- Max.
  • Page 64: Project Planning

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Project planning You will find information for the project planning of a VENTUM PRO LITE with the corresponding pipe system in this chapter. General information The project planning of the VENTUM PRO LITE according to EN 54-20 or ISO 7240-20 is described below.
  • Page 65: Laws, Standards And Guidelines

    5 | Project planning 5.1.1 Laws, standards and guidelines The basic principles for the project planning of a VENTUM PRO LITE can be found in the following laws, standards and guidelines. In addition to these laws, standards and guidelines, the corresponding national laws, standards and guidelines must be observed and the project planning must be adapted to these specifications.
  • Page 66: Table 7 Overview Of The Pipe Shapes

    – Changing direction of the pipe system Pipe connections The VENTUM PRO LITE has two pipe connections. One pipe system may be connected to each of these pipe connections, as long as two detector modules are being used. This means that only one pipe system can be connected if only one detector module is used.
  • Page 67: Image 35 Pipe Shapes

    ▪ The sampling points should be as evenly distributed as possible in the respective branches. Comply with the limit values of the VENTUM PRO LITE for each pipe system of the selected pipe project planning (see chapter "Project planning limits").
  • Page 68: Image 36 Examples Of Symmetrical And Asymmetrical U-Pipe System

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Image 36: Examples of symmetrical and asymmetrical U-pipe system The previous figure shows an example of a U-pipe system with symmetrical or asymmetrical structure and with calculated diameters of the sampling points (see Chapter Determination of sampling points diameter”).
  • Page 69: Image 37 Determine Number Of Sampling Points For Long Branch For Asymmetrical U-Pipe System

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning Example Image 37: Determine number of sampling points for long branch for asymmetrical U- pipe system Image 38: Determine number of sampling points for short branch for asymmetrical U- pipe system The diameters of the sampling points for an asymmetrical U-pipe system (two branches) should be determined.
  • Page 70: Air Flow Monitoring

    One detector module must be allocated per branch. Both detector modules according to VdS 3435 of a device must be analysed separately from each other. Only one extinguishing area may be monitored per VENTUM PRO LITE. Image 39: Example pipe configuration with dual detection dependency 5.1.3...
  • Page 71: Table 8 Overview Of Threshold Values And Sensitivity Of The Air Flow Sensor

    Overview of threshold values and sensitivity of the air flow sensor Dynamic air flow sensors The air flow monitoring of VENTUM PRO LITE enables the system to detect both a breakage at the pipe end and sudden obstruction in individual aspiration apertures (e.g.
  • Page 72: Sensitivity

    Aspirating smoke detector VENTUM PRO LITE 5.1.4 Sensitivity The sensitivity of a VENTUM PRO LITE can be classified into specific fire sensitivity classes according to EN 54-20 or ISO 7240-20. These fire sensitivity classes describe specific example applications in which the devices can be used.
  • Page 73: Project Planning Limits

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning The project planning for the monitoring areas is always carried out in accordance with the national laws, standards and guidelines for point-type smoke detectors. 5.1.5 Project planning limits Observe the following limit values for every pipe system:...
  • Page 74: Project Planning Guidelines

    The following factors must be known for project planning that complies with EN 54-20 or ISO 7240-20: ▪ Requirement for the sensitivity of the VENTUM PRO LITE ▪ Number of aspiration apertures ▪ Pipe accessories required for the corresponding application (e.g.
  • Page 75: Table 12 Air Filter - Type And Areas Of Application

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning ▪ Detector box ▪ Detonation prevention device 5.2.1.1 Detailed pipe accessories Air filter Type Application Examples LF-VE-k Coarse filter to separate Insects, fibres, hair particles ≳30 µm LF-VE Coarse filter to separate Dusts, insects, fibres, particles ≳15 µm...
  • Page 76: Procedure For Pipe Project Planning

    In order to optimise the detection results of a VENTUM PRO LITE, a room can be monitored with more aspiration apertures than required by the national laws, standards and guidelines.
  • Page 77: Table 18 Procedure For Project Planning With Pipe Accessories (Example)

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning 5.2.2.2 Determination of further parameters Example In the following example, the project planning should fulfil the following criteria: ▪ No air filter ▪ Eight sampling point ▪ Fire sensitivity class B ▪...
  • Page 78: Image 40 Project Planning Example

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Image 40: Project planning example Results The following detector modules can be optionally used with the corresponding settings for fire sensitivity class A or B: ▪ DM-VPL-01 - with a sensitivity of at least 0.12% light obscuration/m ▪...
  • Page 79: Determination Of Aspiration Aperture Diameter

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning Pipe shape Fan voltage [V] Max. overall pipe length [m] I-pipe system ≥ 9 U-pipe system ≥ 9 M-pipe system ≥ 9 Double U-pipe system ≥ 9 Table 19: Results of project planning with pipe accessories (example) 5.2.3...
  • Page 80: Image 42 U-Pipe System

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Number of sampling points Item Punch diameter of the aspiration reducing film sheets [mm] Table 20: Diameter of the sampling points for I-pipe systems U-pipe Image 42: U-pipe system Number of sampling points...
  • Page 81: Special Project Planning

    Diameter of the aspiration apertures for double U-pipe systems Special project planning In this chapter, you will find information on the project planning of a VENTUM PRO LITE with the corresponding pipe system, deviating from the previous standard project planning (see Chapter "Project planning guidelines").
  • Page 82: Project Planning With Single Hole Monitoring

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE 5.3.1 Project planning with single hole monitoring According to the pipe shape, the following pipe system parameters are applicable to detect a single or a specific number of blocked sampling points.
  • Page 83: Table 24 Limit Values For Project Planning With Single Hole Monitoring (I-Pipe System)

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning Prerequisite Limit value Min. distance between 2 aspiration apertures (d) [m] Max. distance between 2 aspiration apertures (d) [m] Max. number of aspiration apertures per pipe system [piece] Table 24:...
  • Page 84: Table 26 Threshold Values For Project Planning With Single Hole Monitoring (I-Pipe System)

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Number of aspiration apertures Number of Threshold values blocked aspiration apertures Table 26: Threshold values for project planning with single hole monitoring (I-pipe system) - not possible O is not feasible...
  • Page 85: Image 46 U-Pipe System For Special Project Planning

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning 5.3.1.2 U-pipe system Image 46: U-pipe system for special project planning Threshold values Prerequisite Limit value Min. distance: device <–> T-piece [m] Max. distance: device <–> T-piece [m] Max. branch length [m] With low fan voltage 6.5 and 6.9 V...
  • Page 86: Table 27 Limit Values For Project Planning With Single Hole Monitoring (U-Pipe System)

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Table 27: Limit values for project planning with single hole monitoring (U-pipe sys- tem) Sampling points Number of sampling points Item Punch diameter of the aspiration reducing film sheets [mm]...
  • Page 87: Table 29 Threshold Values For Project Planning With Single Hole Monitoring (U-Pipe System)

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning Number of aspiration apertures Number of Threshold values blocked aspiration apertures Table 29: Threshold values for project planning with single hole monitoring (U-pipe system) - not possible O is not feasible...
  • Page 88: Image 47 M-Pipe System For Special Project Planning

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE 5.3.1.3 M-pipe system Image 47: M-pipe system for special project planning Threshold values Prerequisite Limit value Min. distance: device <–> T-piece [m] Max. distance: device <–> T-piece [m] Max. branch length [m] With low fan voltage 6.5 and 6.9 V...
  • Page 89: Table 30 Limit Values For Project Planning With Single Hole Monitoring (M-Pipe System)

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning Table 30: Limit values for project planning with single hole monitoring (M-pipe sys- tem) Sampling points Number of aspiration apertures Item Punching diameter of the aspiration reducing film sheets [mm]...
  • Page 90: Table 32 Threshold Values For Project Planning With Single Hole Monitoring (M-Pipe System)

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Number of aspiration apertures Number of Threshold values blocked aspiration apertures Table 32: Threshold values for project planning with single hole monitoring (M-pipe system) - not possible O is not feasible...
  • Page 91: Image 48 Double U-Pipe System For Special Project Planning

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning 5.3.1.4 Double U-pipe system Image 48: Double U-pipe system for special project planning Threshold values Prerequisite Limit value Min. distance: device <–> last T-piece [m] Max. distance: device <–> last T-piece [m] Max.
  • Page 92: Table 33 Limit Values For Project Planning With Single Hole Monitoring (Double U-Pipe System)

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Table 33: Limit values for project planning with single hole monitoring (double U-pipe system) Sampling points Number of sampling points Item Punch diameter of the aspiration reducing film sheets [mm]...
  • Page 93: Simplified Project Planning

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning Table 35: Threshold values for project planning with single hole monitoring (double U-pipe system) - not possible O is not feasible Example Blockage of 3 aspiration apertures from a total of 8 aspiration apertures should be detected.
  • Page 94: Image 50 U-Pipe System For Simplified Pipe Project Planning

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Threshold values Prerequisite Threshold value Min. clearance: device <–> first sampling point [m] Max. clearance: device <–> first sampling point [m] Max. distance: first sampling point <–> last sampling points [m] Max.
  • Page 95: Table 38 Threshold Values Of A Simplified Project Planning (U-Pipe System)

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning Threshold values Prerequisite Threshold value Min. distance: device <–> T-piece [m] Max. distance: device <–> T-piece [m] Max. branch length [m] Max. overall pipe length Ø 25 mm [m] Min. distance between 2 sampling points (d) [m] Max.
  • Page 96: Image 51 M-Pipe System For Simplified Pipe Project Planning

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE 5.3.2.3 M-pipe system Image 51: M-pipe system for simplified pipe project planning Threshold values Prerequisite Threshold value Min. distance: device <–> T-piece [m] Max. distance: device <–> T-piece [m] Max. branch length [m] Max.
  • Page 97: Image 52 Double U-Pipe System For Simplified Pipe Project Planning

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning Sampling points Number of sampling points Punch diameter of the aspiration reducing film sheets [mm] Table 41: Diameter of the sampling points with simplified project planning (M-pipe system) 5.3.2.4 Double U-pipe system...
  • Page 98: Project Planning With Stubs

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Prerequisite Threshold value Min. distance between 2 sampling points (d) [m] Max. distance between 2 sampling points (d) [m] Max. number of aspiration apertures per pipe system [piece] Table 42:...
  • Page 99: Image 53 Examples Of Project Planning With Stubs (As I-Pipe System Here)

    ) does not exceed the permissible maximum overall pipe length. The crit. "critical length" with the I-pipe system is defined as the distance between the VENTUM PRO LITE and the most distant aspiration aperture. Image 54: Critical length (I crit.
  • Page 100: Image 55 Determination Of The Critical Length Lcrit. For Pipe Systems With More Than One Branch

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Example Determination of the critical length l for pipe systems with more than one crit. branch (double U-pipe system here): crit. supply 1 supply 2 supply 3 branch 1 branch 2...
  • Page 101: Image 57 Diameter Of Aspiration Apertures

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning Project planning d [m] min. max. Standard Special Chapter "Project planning with single hole monitoring" Chapter "Simplified project planning" Chapter "Project planning with acceleration points" Table 44: Permissible intervals between the sampling points...
  • Page 102: Project Planning With Pipe Supply Lines Ø > 25 Mm

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE 5.3.4 Project planning with pipe supply lines Ø > 25 mm Only Ø 32 or 40 mm pipes may be used for the planning of supply pipe lines with larger diameters. The pipe supply line is described as the pipe system between the device and the first sampling point (I-pipe system) or the last T- piece (U, M and double U-pipe system).
  • Page 103: Image 60 I-Pipe With Acceleration Opening

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning 5.3.5.1 I-pipe system Image 60: I-pipe with acceleration opening Number of sampling points Item Punch diameter of the aspiration reducing film sheets [mm] Table 45: Diameter of the sampling points for I-pipe system with acceleration points AO = acceleration point = 7.0 mm...
  • Page 104: Image 61 U-Pipe With Acceleration Openings

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Number of sampling points Item Punch diameter of the aspiration reducing film sheets [mm] Table 46: Diameter of the sampling points for I-pipe system with acceleration points AO = acceleration point = 7.0 mm * = acceleration point = 7.0 mm...
  • Page 105: Image 62 M-Pipe With Acceleration Openings

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning Number of aspiration apertures Item Punching diameter of the aspiration reducing film sheets [mm] Table 47: Diameter of the aspiration apertures for U-pipe system with acceleration openings AO = acceleration point = 7.0 mm * = acceleration point = 7.0 mm...
  • Page 106: Image 63 Double U-Pipe With Acceleration Openings

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Number of aspiration apertures Item Punching diameter of the aspiration reducing film sheets [mm] Table 48: Diameter of the aspiration apertures for M-pipe system with acceleration openings AO = acceleration point = 7.0 mm * = acceleration point = 7.0 mm...
  • Page 107: Project Planning With Forced Air Flow

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning 5.3.6 Project planning with forced air flow Monitoring of air-conditioning Air conditioning systems are distinguished between low-speed and high- ducts speed systems. Low-speed systems High-speed systems Flow speed [m/s] max. 6 … 10 >10...
  • Page 108: Image 65 Change In Direction In The Air-Conditioning Duct Without Baffles

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Aspiration The pipe system in the air-conditioning duct must be arranged in the speed areas V … V to achieve optimum detection results. Installation location of the pipe The exhaust air duct must be selected as the installation location for the pipe system system.
  • Page 109: Image 66 Silencer In Air-Conditioning Duct

    The following must be observed when installing pipe systems in air- conditioning ducts: ▪ Air return is required as the VENTUM PRO LITE and the pipe system are located in areas with different air pressures. ▪ The pipe inlets in the air-conditioning duct must be sealed to be airtight.
  • Page 110: Image 67 Air Return In The Air-Conditioning Duct

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Image 67: Air return in the air-conditioning duct 1 Air-conditioning duct 2 Aspiration 3 VENTUM PRO LITE 4 Air return 5 Duct adapter 6 Airflow 7 45° chamfered end The pipes must be offset if the distance of 2 m cannot be adhered to. In this way, a pressure drop between the supply air and the exhaust air is achieved as the pipes are located in different speed ranges.
  • Page 111: Image 68 Offset Arrangement Of The Air Return Line

    Aspirating smoke detector VENTUM PRO LITE 5 | Project planning Image 68: Offset arrangement of the air return line 1 Air-conditioning duct 2 Duct adapter 3 Aspiration in the speed range V 4 VENTUM PRO LITE 5 Airflow 6 Return in the speed range V...
  • Page 112: Project Planning With Aspiration Hose

    5 | Project planning Aspirating smoke detector VENTUM PRO LITE Example Image 69: Ducts with small duct cross-section Image 70: Ducts with large duct cross-section 5.3.7 Project planning with aspiration hose The use of aspiration hoses can make sense if several changes of direction are required in a pipe system over short distances (e.g.
  • Page 113: Table 52 Factor A For Aspiration Hose Type Sch

    For the pipe project planning, a total of 100 m aspiration pipe and aspiration hose is connected to a VENTUM PRO LITE with a fan voltage of 6.5 V. The permissible overall pipe length for the entire pipe project planning can be 120 m according to the project planning table.
  • Page 114: Project Planning With Air Return

    5.3.8 Project planning with air return If the VENTUM PRO LITE and the pipe system are installed in areas with different air pressure, return of the aspirated air into the pipe system pressure area is required. For this, a correspondingly long aspiration pipe must be connected to the air outlet of the VENTUM PRO LITE.
  • Page 115: Energy Supply

    NOTE No standard conformity in case of wrong energy supply The energy supply of the VENTUM PRO LITE must be approved in accordance with EN 54-4 or ISO 7240-4. When configuring the external energy supply, the alarm-ready state and the alarm state of the connected devices are taken into account.
  • Page 116 5 | Project planning Aspirating smoke detector VENTUM PRO LITE Variable Unit Description Alarm current Number of devices Alarm current of device Number of accessories 1 Alarm current/current consumption of accessories 1 Number of accessories i Alarm current/current consumption of accessories i...
  • Page 117 Aspirating smoke detector VENTUM PRO LITE 5 | Project planning Observe the relevant national laws, standards and guidelines. In Germany, for example, the following apply: DIN VDE 0833 and/or VdS 2095. In accordance with these laws, standards and guidelines, a hold-up time of 30 h (under certain conditions 4 h) with a subsequent alarm time of 0.5 h...
  • Page 118 5 | Project planning Aspirating smoke detector VENTUM PRO LITE Variable/const Unit Description Charge current 80% in 24 h Nominal battery capacity Charging factor due to thermal losses when charging the backup batteries Power supply current Variable Unit Description Power supply current for alarm-ready state...
  • Page 119 Aspirating smoke detector VENTUM PRO LITE 5 | Project planning LITERATURE You will find information on the end-point voltage in the technical data of the energy supply in use. Refer to the chapter "Technical data" for the supply voltage of the VENTUM PRO LITE.
  • Page 120: Installation

    6 | Installation Aspirating smoke detector VENTUM PRO LITE Installation You will find information about installing the VENTUM PRO LITE and the pipe system in this chapter. General information The regulations, guidelines and terms listed in chapter "Requirements" apply. The following must be observed when installing the device: ▪...
  • Page 121: Determination Of Installation Location

    ▪ No surrounding components (e.g. wall projections) obstruct the air inlet or air outlet. Installation of device You must install the VENTUM PRO LITE either with the bottom part of the housing directly to a wall or using a special bracket. IK-E392-001-GB...
  • Page 122 1 Aspiration pipe 2 Angled pipe 3 Air return 4 VENTUM PRO LITE with top air outlet 5 VENTUM PRO LITE with bottom air outlet The device can be installed with the air inlet pointing up or down. Rotate the cover accordingly by 180°.
  • Page 123: Table 56 Installation Materials For Installation Of Device

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation Installation materials Wall mounting Installation with brackets 4x cylinder or flat-head screws 4x cylinder or flat-head screws • Thread diameter max. 6 mm • Thread diameter 4 mm • Head diameter max. 10 mm 4x washers •...
  • Page 124 6 | Installation Aspirating smoke detector VENTUM PRO LITE Installation with brackets Image 73: Device brackets Image 74: Drill hole intervals [mm] for bracket type MT-1 ► Fix the brackets onto the device. ► Mark the drilling intervals on the corresponding installation surface (e.g.
  • Page 125: Opening The Device

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation ► Drill the holes according to the size of the suitable installation material (screws/plugs). ► Tighten the four screws by hand. It must be ensured that the device is installed mechanically stress-free.
  • Page 126: Making Settings

    ► Put the housing cover to one side. Ensure that the housing cover is neither soiled nor damaged. Making settings The settings of the VENTUM PRO LITE are made via the detector modules by means of DIL switches. IK-E392-001-GB...
  • Page 127: Setting The Response Sensitivity (Main Alarm)

    6.5.2 Setting the delay time of the alarm trigger If the smoke level rises during operation of the VENTUM PRO LITE up to one of the alarm thresholds, the delay time starts to run. The signal is only transferred with the alarm still pending after expiration of the delay time. This means that a false alarm can be prevented in case of short-term loads (e.g.
  • Page 128: Setting The Trigger Threshold For The Air Flow Monitoring

    6 | Installation Aspirating smoke detector VENTUM PRO LITE Delay period DIL switch S1 Contact 3 Contact 4 10 (standard) Table 58: Alarm trigger delay time 6.5.3 Setting the trigger threshold for the air flow monitoring Select the trigger threshold of the air flow fault according to the chapter "Project planning".
  • Page 129: Activating Or Deactivating The Memory Fault Display

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation Delay time DIL switch S1 Contact 7 Contact 8 120 s (standard) 15 min 60 min Table 60: Delay time for the air flow fault Permissible according to 54-20/ISO 7240-20 6.5.5...
  • Page 130: Setting The Contact Type Of The Collective Fault

    6 | Installation Aspirating smoke detector VENTUM PRO LITE 6.5.7 Setting the contact type of the collective fault NOTE Danger of short circuit on the motherboard Only perform the following work with the device disconnected from the mains. Image 77:...
  • Page 131: Setting And Connecting The Fan

    Setting and connecting the fan The fan voltage must be set according to project specifications before connecting the fan. The different settings and connection diagrams for VENTUM PRO LITE and VENTUM PRO LITE-SL must be observed. 6.6.1 Switching the fan voltage In critical monitoring areas, the fan voltage can be increased to shorten the transport time of the smoke aerosols in the aspiration pipe.
  • Page 132: Connecting The Fan

    VENTUM PRO LITE basic board. Image 80: Connect the fan to the basic board Upon delivery of the VENTUM PRO LITE, the fan was connected in the factory. ► Connect the red fan connection cable to terminal strip X5 / terminal 1 (+).
  • Page 133: Switching The Fan Voltage For The Sl Version

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation ► Connect the black fan connection cable to terminal strip X5 / terminal 2 (-). 6.6.3 Switching the fan voltage for the SL version The default setting for the fan voltage is 6.9 V (FC-2) or 11 V (FC-3). The fan voltage can be adjusted according to project planning by plugging or removing the BR1 and/or BR2 bridges.
  • Page 134: Connecting The Fan For The Sl Version

    3 LED 4 Connection for flat ribbon cable 6.6.4 Connecting the fan for the SL version The electrical connection of the fan control circuit board is made using terminal strip X5 (FAN) on the VENTUM PRO LITE basic board. IK-E392-001-GB...
  • Page 135 Image 85: Connecting the fan to the fan control circuit board type FC-2 or FC-3 Upon delivery of the VENTUM PRO LITE, the fan was connected in the factory. ► Connect terminal strip X5 / terminal 1 on the basic board to terminal strip X2 / terminal 2 (+) on the fan control circuit board.
  • Page 136: Inserting And Connecting Detector Module I

    6 | Installation Aspirating smoke detector VENTUM PRO LITE ► Connect the purple fan connection cable to terminal strip X1 / terminal 3 of the fan control circuit board. Inserting and connecting detector module Image 86: Opening the device 1 Housing cover...
  • Page 137 Aspirating smoke detector VENTUM PRO LITE 6 | Installation NOTE Danger of short circuit on the motherboard Only perform the following work with the device disconnected from the mains. NOTE Electrostatic discharge due to contact Protect the components of the main circuit board from damage due to static discharge.
  • Page 138 6 | Installation Aspirating smoke detector VENTUM PRO LITE Image 87: Connections on basic board X1, X3 and X4 ► Connect the flat ribbon cable of the display circuit board to the basic board (connection X4 (DISPLAY)). Ensure the marking pin is positioned correctly before plugging the ribbon cable plug into the basic board.
  • Page 139: Inserting And Connecting Detector Module Ii

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation Inserting and connecting detector module NOTE Danger of short circuit on the motherboard Only perform the following work with the device disconnected from the mains. ► Carefully unlock the quick-action fasteners on the housing using a flat- head screwdriver by simultaneously pressing in the closing flaps located on one side.
  • Page 140 6 | Installation Aspirating smoke detector VENTUM PRO LITE Image 89: Insert detector module II 1 Fan cover 2 Retaining clips 3 Detector module 4 Basic board ► Carefully break the seal on the housing for connection of the second pipe system (predetermined breaking point marked with "II") by using a...
  • Page 141 Aspirating smoke detector VENTUM PRO LITE 6 | Installation module and audibly engage. Only use type DM-VPL-xx detector modules (green type plate). ► Then press both retaining clips together again. ► Unplug the jumper JU4 from the basic board. Image 91: Unplugging the jumper JU4 from the basic board ►...
  • Page 142 4 Connection for flat ribbon cable ► Close the cover. Ensure that none of the ribbon cables are squashed. ► Let the quick-action fasteners click into place. With an extension to VENTUM PRO LITE TWO: ► Replace the front film sheet. IK-E392-001-GB...
  • Page 143: Inserting And Connecting The Reset Circuit Board

    The VENTUM PRO LITE enables the use of maximum one optional reset circuit board. If several VENTUM PRO LITE are connected to a detector line, a reset circuit board is only used in the last device of the detector line. A...
  • Page 144: Image 96 Position Of The Reset Circuit Board

    6 | Installation Aspirating smoke detector VENTUM PRO LITE Image 96: Position of the reset circuit board 1 Mounting plate 2 Reset circuit board Calculation Standby current of the detector The standby current I of the detector line must be calculated as shown...
  • Page 145 Aspirating smoke detector VENTUM PRO LITE 6 | Installation Variable/const Unit Description Ω Resistor (ER = End Reset) Detector line voltage (DL = Detector Line) Voltage loss within the reset circuit board Standby current of the detector line (DL = Detector Line)
  • Page 146: Image 97 Inserting The Termination Resistor In The Reset Circuit Board

    6 | Installation Aspirating smoke detector VENTUM PRO LITE Image 97: Inserting the termination resistor in the reset circuit board ► Fixing the reset circuit board to the mounting plate (installation kit for additional module type KT-HS-1) with two plastic spacers (enclosed with the reset circuit board).
  • Page 147: Image 99 Opening The Device

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation Image 99: Opening the device 1 Housing cover 2 Display circuit board (not visible) 3 Quick-action fasteners 4 Connection: X1 HEAD 1 5 Connection: X4 DISPLAY 6 Basic board 7 Retaining clips 8 Detector module ►...
  • Page 148: Establishing The Electrical Connection

    6 | Installation Aspirating smoke detector VENTUM PRO LITE ► Connect the flat ribbon cable of the display circuit board to the basic board (connection X4 (DISPLAY)). Ensure the marking pin is positioned correctly before plugging the ribbon cable plug into the basic board.
  • Page 149: Connecting To An Fdcp, With Reset Button

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation NOTE Danger of short circuit on the motherboard Only perform the following work with the device disconnected from the mains. NOTE Maximising fault protection In order to maximise fault protection, use shielded cables for the external wiring of the device (e.g.
  • Page 150: Image 102 Example Connection To An Fdcp With Reset Button

    6 | Installation Aspirating smoke detector VENTUM PRO LITE ▪ for connection on a fire detection control panel ▪ for the control of signal transmitters, control systems etc. ▪ for connection of response indicators The "Reset" input must not be permanently connected with +24 V.
  • Page 151: Connecting To An Fdcp, With Reset Circuit Board

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation L1 … L4 Detector line connection Resistors depend on the connected fire detection control panel. The fault contacts (N/C or N/O) are set via jumpers on the basic board. ▪ JU2 = detector module I ▪...
  • Page 152: Image 103 Example Connection To Fdcp With Reset Circuit Board

    6 | Installation Aspirating smoke detector VENTUM PRO LITE Image 103: Example connection to FDCP with reset circuit board L1 … L4 Detector line connection Resistors depend on the connected fire detection control panel. These resistors must be calculated (see chapter "Inserting and connecting the reset circuit board").
  • Page 153: Connecting Without An Fdcp, With Reset Button

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation ▪ JU3 = detector module II The following applies: ▪ JU2/JU3 contact 1+2 = N/C (standard) ▪ JU2/JU3 contact 2+3 = N/O Connecting without an FDCP, with reset button 6.10.3 The "Reset" input must not be permanently connected with +24 V.
  • Page 154: Image 104 Example Connection (Without An Fdcp) With Reset Button

    6 | Installation Aspirating smoke detector VENTUM PRO LITE Image 104: Example connection (without an FDCP) with reset button The fault contacts (N/C or N/O) are set via jumpers on the basic board. ▪ JU2 = detector module I ▪ JU3 = detector module II The following applies: ▪...
  • Page 155: Connecting Response Indicators

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation 6.11 Connecting response indicators Image 105: Response indicators FDAI-91 and FDAI-92 The electrical connection is established via the basic board of the VENTUM PRO LITE. ▪ Response indicator for detector module 1: X6:4 and 5 ▪...
  • Page 156: Image 106 Connecting The Response Indicator

    6 | Installation Aspirating smoke detector VENTUM PRO LITE Image 106: Connecting the response indicator 1 Quick-action fasteners 2 Basic board 3 Connecting terminals X6/X7 ► Carefully unlock the quick-action fasteners on the housing using a flat- head screwdriver by simultaneously pressing in the closing flaps located on one side.
  • Page 157: Data Logging

    ▪ ... to perform a test of the VENTUM PRO LITE. ▪ ... to save all current and stored data as well as settings made in the VENTUM PRO LITE as a file or in an automatically created log, see chapter "Function test".
  • Page 158: General Information On The Pipe System

    6 | Installation Aspirating smoke detector VENTUM PRO LITE Image 108: Connect diagnostic interface 1 Service PC 2 USB connection cable 3 Diagnostic interface 4 Diagnostics interface connection cable 5 Basic board VENTUM PRO LITE ► Store and archive the files for later comparison. Make sure to save each file under another file name.
  • Page 159: Table 67 Characteristics Of The Aspiration Pipes And Hoses To Be Used

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation NOTE Changing the length of pipe lines For the setup of the pipe system, note the temperature difference at the time of installation and the later use of the monitoring area (see chapter "Pipe system").
  • Page 160: Length Alterations On The Pipe System

    6 | Installation Aspirating smoke detector VENTUM PRO LITE Minimise the pipe lengths and changes of direction. An excessive number of pipe elbows and angles reduces the air flow speed in the aspiration pipe, thus increasing the detection time. It is better to use pipe elbows than pipe angles.
  • Page 161: Image 109 Pipe Clip Standard Type Ng Xx

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation 6.13.1.1 Pipe clips Type NG xx Image 109: Pipe clip standard type NG xx For the first pipe clip after the device, use a type that does not permit length extension of the pipe. The following plastic pipe clips are used as standard: ▪...
  • Page 162: Installation Of The Pipe System

    6 | Installation Aspirating smoke detector VENTUM PRO LITE The spring steel clips are available for the following three profile sizes: ▪ 1 … 4 mm ▪ 4 … 7 mm ▪ 8 … 12 mm Spring steel clips (type SNAP CLIP-SC) are used for high-bay warehouses and refrigerated areas.
  • Page 163: Installation Of The Aspiration Pipe

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation - faulty connections - correct execution of the sampling points in accordance with the project specifications 6.15 Installation of the aspiration pipe Image 112: Installation of the aspiration pipe NOTE Hazard of bending or rupturing pipe lines Do not use pipe clips with rubber inserts as they do not permit length extensions, meaning that the pipe system would bend or even rupture.
  • Page 164 6 | Installation Aspirating smoke detector VENTUM PRO LITE The overall aspiration pipe cannot consist of aspiration hoses alone. No openings may be drilled in the suction hoses and no aspiration reductions may be made to the suction hoses. ► Crop the suction hose using a pipe cutter, pipe shears or a metal saw.
  • Page 165: Installation Of Aspiration Apertures

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation 6.17 Installation of aspiration apertures Image 113: Aspiration aperture, aspiration-reducing film sheet and marking tape 1 Aspiration-reducing film sheet 2 Air sampling pipe (pipe system) 3 Aspiration aperture Ø 25/64" (10 mm)
  • Page 166: Installation Of The Ceiling Feed-Throught

    6 | Installation Aspirating smoke detector VENTUM PRO LITE WARNING Risk of injury due to flammable liquids and vapours Formation of explosive/highly flammable vapour/air mixtures is possible. Injuries to health due to direct or indirect contact. ► Prior to processing, observe the safety notes of the manufacturer.
  • Page 167: Installation Of The Ceiling Feed-Throught

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation 6.18.1 Installation of the ceiling feed-throught Image 114: Overview of ceiling feed-throught components 1 Elbow 90° 2 Ceiling feed-throught set (3-part) 2a Hose nozzle 2b Nut 2c Ceiling feed-throught 3 Aspiration reducing film sheet...
  • Page 168: Image 115 Aspiration Pipe, Elbow And Hose Nozzle

    6 | Installation Aspirating smoke detector VENTUM PRO LITE WARNING Risk of injury due to flammable liquids and vapours Formation of explosive/highly flammable vapour/air mixtures is possible. Injuries to health due to direct or indirect contact. ► Prior to processing, observe the safety notes of the manufacturer.
  • Page 169: Installation Of The Ceiling Feed-Throught For Special Applications

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation ► Cut the capillary hose using the hose shears. ► Attach the cut capillary hose to the ceiling feed-throught and to the hose nozzle. Heat the capillary hose with a hot air blower of necessary.
  • Page 170: Image 118 Ceiling Feed-Throught With Upstream Aspiration Reducing Film Sheet

    6 | Installation Aspirating smoke detector VENTUM PRO LITE NOTE Missing monitoring for rupture The capillary hose cannot be monitored for rupture in case of the special application of ceiling feed-throughts in which the aspiration reducing film sheets are upstream in T-pieces (pipe hoods).
  • Page 171: Image 119 Pipe System, T-Piece And Hose Nozzle

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation NOTE Detach aspiration-reducing film sheets Should aspiration-reducing film sheets become partially or completely detached from the aspiration pipe, detection in accordance with the project specifications cannot be guaranteed. ► Avoid any contact with the adhesive surfaces to keep these free from dust and grease.
  • Page 172: Installation Of Pipe System On Forced Airflow Monitoring

    6 | Installation Aspirating smoke detector VENTUM PRO LITE ► Attach the cut capillary hose to the ceiling feed-throught and to the hose nozzle. Heat the capillary hose with a hot air blower of necessary. ► Glue the capillary hose into the drilled hole of the suspended ceiling using Tangit glue.
  • Page 173: Detection Of Supply And Exhaust Air Openings

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation 6.19.1 Detection of supply and exhaust air openings Image 121: Detection of supply and exhaust air openings, e.g. air grille 1 Air-conditioning duct 2 Airflow 3 Air grille (exhaust air opening)
  • Page 174: Detection In The Bypass

    3 Airflow 6.19.2 Detection in the bypass For project planning of the VENTUM PRO LITE in areas with forced air flow, see chapter "Project planning with forced air flow". Refer to the chapter "Installation of air return" for information on connecting the air return.
  • Page 175: Installing The Air Filter/Special Filter

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation Image 123: Detection in the bypass 1 Air-conditioning duct 2 Airflow 3 Aspiration apertures 4 Aspiration pipe 5 VENTUM PRO LITE 6 Air return 7 Duct adapter 8 45° angle (at the open end of the air return) 6.20...
  • Page 176 6 | Installation Aspirating smoke detector VENTUM PRO LITE Image 124: Air filter type LF-VE and LF-VE-x Installation materials Cylinder or flat-head screws ▪ Thread diameter max. 4 mm ▪ Head diameter 5 … 7 mm ► Insert the aspiration pipe in the provided pipe connection of the bottom part of the housing.
  • Page 177: Installing Air Filter Type Lf-Ve-K

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation Image 126: Drilling intervals air filter type LF-VE and LF-VE-x ► Drill the holes according to the size of the suitable installation material (screws/plugs). ► Tighten the four screws by hand. It must be ensured that the device is installed mechanically stress-free.
  • Page 178 6 | Installation Aspirating smoke detector VENTUM PRO LITE glued together with the pipe connection for service purposes or for the replacement of the device. Also please observe the flow direction that is specified on the rating plate on the bottom part of the housing.
  • Page 179: Installing Special Filter Type Sf-400 Or Sf-650

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation 6.20.3 Installing special filter type SF-400 or SF-650 Image 130: Installing the special filter 1 Clamp 2 45° angle 3 PVC transition screw connection 4 Special filter type SF-400, SF-650 ► Glue a pipe section into the transition screw connections.
  • Page 180: Installing Special Filter And Air Filter In Combination

    6 | Installation Aspirating smoke detector VENTUM PRO LITE 6.20.4 Installing special filter and air filter in combination Image 131: Installing special filter and air filter in combination 1 VENTUM PRO LITE 2 Special filter type SF-400, SF-650 3 Air filter type LF-VE, LF-VE-1, LF-VE-2...
  • Page 181: Installation Of Air Return

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation 6.21 Installation of air return Image 132: Installation of air return 1 VENTUM PRO LITE 2 Air return ► Remove the pre-stamped pipe opening in the safety guard of the air outlet, e.g.
  • Page 182 6 | Installation Aspirating smoke detector VENTUM PRO LITE Image 133: Silencer type SD-1-P ► Insert the aspiration pipe in the provided pipe connection of the bottom part of the housing. Please note that the aspiration pipe must not be glued together with the pipe connection for service purposes or for the replacement of the device.
  • Page 183: Installation Of 3-Way Ball Valve

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation Image 135: Drilling intervals for silencer type SD-1-P ► Drill the holes according to the size of the suitable installation material (screws/plugs). ► Tighten the four screws by hand. It must be ensured that the device is installed mechanically stress-free.
  • Page 184 6 | Installation Aspirating smoke detector VENTUM PRO LITE Image 136: Installation of 3-way ball valve 1 Compressed air connection 2 3-way ball valve 3 Pipe system 4 Air filter (optional) 5 Device open closed The 3-way ball valve is fixed in the pipe system by means of transition screw connections.
  • Page 185: 3-Way Ball Valve (Abs/Pvc)

    Aspirating smoke detector VENTUM PRO LITE 6 | Installation 6.23.2 3-way ball valve (ABS/PVC) It switches between fire detection (90° position) and purging (270° position). Image 137: Installing a 3-way ball valve made of ABS/PVC 1 Compressed air connection 2 3-way ball valve...
  • Page 186: Installation Of The Condensate Separator

    6 | Installation Aspirating smoke detector VENTUM PRO LITE The 3-way ball valve is fixed in the pipe system by means of transition screw connections. Observe the allocation of the connections as defined in the scheme of the 3-way ball valve.
  • Page 187 Aspirating smoke detector VENTUM PRO LITE 6 | Installation The condensate separator is installed in the pipe system at the lowest point of the pipe system upstream of an air filter (optional) and the VENTUM PRO LITE. For optimum wall spacing, four 45° angles are required for installation of the condensate separator in the pipe system.
  • Page 188: Condensate Separator Type Ka-1-P

    6 | Installation Aspirating smoke detector VENTUM PRO LITE 6.24.2 Condensate separator type KA-1-P Image 139: Steam trap type KA-1-P 1 Steam trap 2 Pipe system 3 Air filter (optional) 4 VENTUM PRO LITE The condensate separator can be used manually as well as automatically.
  • Page 189: Installation Of Detonation Prevention Device

    WARNING Danger of pipe deflagration or detonation The VENTUM PRO LITE must not be mounted in areas with a potentially explosive atmosphere. Non-observance could lead to an ignition of the explosive atmosphere due to static discharge. The following is to be discussed with an expert in advance: ▪...
  • Page 190 The pipes used in the Ex area are installed on the detonation protector via a transition screw connection. The steel aspiration pipes used between the VENTUM PRO LITE and the detonation protectors are mounted to the detonation protectors via screw-in connections. The connections must be established by means of a ¾“...
  • Page 191 ► Install the detonation protectors with a minimum distance of 1 m from the VENTUM PRO LITE in the aspiration and air return pipe. ► Connect the VENTUM PRO LITE and the detonation protectors via the screw-in connections on the steel aspiration pipe (type R-2525).
  • Page 192: Installation Of Test Adapter

    6 | Installation Aspirating smoke detector VENTUM PRO LITE ► Seal the threaded connections with Synthesol or sealing tape. ► Earth the pipe system depending on its material. 6.26 Installation of test adapter A test adapter must be installed upstream of the air inlet of a VENTUM PRO LITE.
  • Page 193 Aspirating smoke detector VENTUM PRO LITE 6 | Installation ► Before gluing into place, free the cut edges from dirt and grease with Tangit cleaner. ► Glue the test adapter in the pipe system in the immediate proximity of the device with Tangit glue.
  • Page 194: Commissioning

    All stored and current diagnostic data as well as settings made of the VENTUM PRO LITE can be saved in the form of a file or an automatically created log using the diagnostic software. Store and archive every file under another file name for the purpose of later comparison.
  • Page 195: Calibration Of Air Flow Sensor

    Use the air pressure correction tables for this purpose (see chapter "Annex"). The initialisation phase of the VENTUM PRO LITE takes approx. 10 s. Once air flow initialisation has finished, the operating LED is permanently illuminated and the air flow sensor has determined its target value for the connected pipe system.
  • Page 196: Air Pressure-Independent Calibration

    LED flashes. Image 143: Trimming potentiometer and measuring points on the basic board 1 Basic board 2 Detector module ► Make sure that the VENTUM PRO LITE is in operation for at least 30 min. IK-E392-001-GB...
  • Page 197: Air Pressure-Dependent Calibration

    A barometer, temperature gauge and a multimeter are required for air pressure-dependent calibration of the air flow sensor. ► Make sure that the VENTUM PRO LITE is in operation for at least 30 min. ► Enter all values determined in the following steps into the test record (see chapter "Annex").
  • Page 198: Checking The Detector Module And The Alarm Transmission

    7 | Commissioning Aspirating smoke detector VENTUM PRO LITE ► Determine the altitude above sea level of the installation location of the VENTUM PRO LITE. ► Measure the air pressure with the barometer. Make sure that the airflow sensor is not adjusted to 0 % if the measured air pressure does not correspond to the level of the corresponding annual mean.
  • Page 199: Checking The Air Flow Monitoring And Fault Signal Transmission

    Aspirating smoke detector VENTUM PRO LITE 7 | Commissioning Accelerating the test Detector module testing and alarm signal transmission can be accelerated. For this, contact 10 of DIL switch S1 on the detector module must be set to OFF. ► Check and, if necessary, change the switch position (S1, contact 10) on the detector module for LOGIC-SENS.
  • Page 200 7 | Commissioning Aspirating smoke detector VENTUM PRO LITE ▪ Blockage: LED flashes 2x ► Make sure that air flow sensor calibration has been carried out (see chapter "Calibration of airflow sensor"). ► Enter all values determined in the following steps into the test record (see chapter "Annex").
  • Page 201: Function Test

    If the device cannot be calibrated, check its functionality using the test pipe and a digital pressure gauge or the diagnostic software. 7.4.1 Preparing for the function test Carry out the preparation for a function test of the VENTUM PRO LITE TWO for both pipe systems. IK-E392-001-GB...
  • Page 202 6 Pressure measurement hose 7 Adapter 8 Digital fine pressure gauge (example) ► Make sure that the VENTUM PRO LITE is in operation for at least 30 min. ► Disconnect the pipe system from the device. ► Connect the test pipe.
  • Page 203: Performing The Function Test

    For a VENTUM PRO LITE TWO, carry out a function test for both pipe systems. A breakage or blockage in the pipe system is displayed on any connected FDCP or by a flash code via LED on the detector module.
  • Page 204 ► Connect VENTUM PRO LITE and the service PC via connection X2 (Diag.) on the basic board of the device using a 6-pin ribbon cable. ► Start the diagnostic software. ➜ The current data from the VENTUM PRO LITE is shown on the service PC screen. IK-E392-001-GB...
  • Page 205 All stored and current diagnostic data as well as settings made of the VENTUM PRO LITE can be saved in the form of a file or an automatically created log using the diagnostic software. Store and archive every file under another file name for the purpose of later comparison.
  • Page 206: Maintenance

    Maintenance intervals The servicing includes regular maintenance. The VENTUM PRO LITE is initially inspected during commissioning and then annually. The national laws, standards and guidelines regarding the applications and project specifications must also be taken into account.
  • Page 207: Flash Codes

    Aspirating smoke detector VENTUM PRO LITE 8 | Maintenance ▪ ... the pipe system is freely accessible. ▪ ... the pipe system is securely installed and undamaged (if accessible). ▪ … the aspiration apertures of the pipe system are clear.
  • Page 208: Checking The Detector Module And The Alarm Transmission

    During start-up and purging, compressed air is applied that can result in damage to the air flow sensor. ► Preferably use a 3-way ball valve. ► Disconnect the VENTUM PRO LITE from the pipe system prior to purg- ing. ► Check the aspiration apertures of the pipe system for blockage in monitoring areas where dust particles or icing are possible.
  • Page 209: Purging The Pipe System

    Aspirating smoke detector VENTUM PRO LITE 8 | Maintenance 8.5.1 Purging the pipe system NOTE Damage to the airflow sensor Disconnect the device from the pipe system before purging the pipe system and the sampling points. Complete the individual purging processes within 50 s. If another purging process is required, repeat the above procedure after 120 s at the earliest.
  • Page 210 8 | Maintenance Aspirating smoke detector VENTUM PRO LITE 1 Device 2 Pipe system 3 3-way ball valve 4 Quick-action coupling sleeve A Compressed air B Air flow for purging open closed ► Connect the compressed air supply using the transition screw connection to the 3-way ball valve.
  • Page 211: Image 148 Manual Air Purge System With 3-Way Ball Valve Made Of Abs Or Pvc

    Aspirating smoke detector VENTUM PRO LITE 8 | Maintenance 3-way ball valve made of ABS/PVC Image 148: Manual air purge system with 3-way ball valve made of ABS or PVC 1 Device 2 Pipe system 3 3-way ball valve (ABS/PVC)
  • Page 212: Replacing The Detector Module

    8 | Maintenance Aspirating smoke detector VENTUM PRO LITE ► Purge the pipe system manually for approx. 10 s. ► Move the lever of the 3-way ball valve to the 0°/180°setting. In this position, the device is neither connected to the pipe system nor to the connection for compressed air.
  • Page 213: Image 149 Replacing The Detector Modules

    Aspirating smoke detector VENTUM PRO LITE 8 | Maintenance Image 149: Replacing the detector modules 1 Housing cover 2 Display circuit board (not visible) 3 Quick-action fasteners 4 Detector module 5 Basic board 6 Retaining clips 7 Connection for ribbon cable of the display circuit board...
  • Page 214: Image 150 Connections On Basic Board X1, X3 And X4

    8 | Maintenance Aspirating smoke detector VENTUM PRO LITE ► Lift the housing cover. ► Carefully loosen the ribbon cable of the display board from the motherboard. ► Put the housing cover to one side. Ensure that the housing cover is neither soiled nor damaged.
  • Page 215: Image 151 Connect The Power Supply

    Aspirating smoke detector VENTUM PRO LITE 8 | Maintenance Image 151: Connect the power supply ► Make sure that the VENTUM PRO LITE is in operation for at least 30 min. ► Press the Flow Init button on the detector module. Image 152:...
  • Page 216: Changing The Filter Inserts Of The Air Filter Type Lf-Ve-X

    8 | Maintenance Aspirating smoke detector VENTUM PRO LITE Changing the filter inserts of the air filter type LF-VE-x Opening the filter after the expiry of the adjusted delay time will lead to an air flow fault. Image 153: Replacing the filter inserts of the air filter type LF-VE-x...
  • Page 217: Replacing The Filter Inserts Of The Special Filter Type Sf-400/Sf-650

    Aspirating smoke detector VENTUM PRO LITE 8 | Maintenance ► Loosen the four cover screws using a slotted screwdriver. ► Put the housing cover to one side. Ensure that the housing cover is neither soiled nor damaged. ► Remove the filter inserts.
  • Page 218: Image 154 Replacing The Filter Elements

    8 | Maintenance Aspirating smoke detector VENTUM PRO LITE Image 154: Replacing the filter elements 1 Pipe system 2 Special filter type SF-400, SF-650 3 PVC transition screw connections 4 VENTUM PRO LITE 5 Screw-in plugs 6 Filter element 7 Filter housing ►...
  • Page 219: Checking The Air Flow Sensor Calibration

    Aspirating smoke detector VENTUM PRO LITE 8 | Maintenance Checking the air flow sensor calibration The value of the air flow sensor must be checked using diagnostic software during servicing. Principle During the initialisation of the connected pipe system, the device initially saves the measured actual value of the air flow as a target value via the integrated air flow monitoring.
  • Page 220 8 | Maintenance Aspirating smoke detector VENTUM PRO LITE The current air flow value may deviate from the target value not only due to a fault in the pipe system (breakage or blockage), but also due to air pressure fluctuations in the surrounding area.
  • Page 221: Checking The Air Flow Monitoring And Fault Signal Transmission

    Aspirating smoke detector VENTUM PRO LITE 8 | Maintenance 8.10 Checking the air flow monitoring and fault signal transmission A breakage or blockage is displayed by a flash code on each detector module (LED). ► Check the airflow monitoring (see Chapter "Commissioning" and "Checking the airflow monitoring and fault transmission").
  • Page 222: List Of Figures

    Displays and connections ....................Image 8 Front panel VENTUM PRO LITE and VENTUM PRO LITE-SL ........Image 9 Front panel VENTUM PRO LITE TWO and VENTUM PRO LITE TWO-SL ....Image 10 Functional principle of detector box (dual detection dependency) ........Image 11 Functional principle of detector box (localisation and increase of the response sensi- tivity) ..........................
  • Page 223 Aspirating smoke detector VENTUM PRO LITE List of figures Image 23 Ceiling feed-throught ....................... Image 24 Ceiling feed-throught for special applications ..............Image 25 Air and special filter ......................Image 26 Filter LF-VE in multiple aspiration branches ..............Image 27 Filter LF-VE in auxiliary branch ..................
  • Page 224 List of figures Aspirating smoke detector VENTUM PRO LITE Image 47 M-pipe system for special project planning ..............Image 48 Double U-pipe system for special project planning ............Image 49 I-pipe system for simplified pipe project planning ............Image 50 U-pipe system for simplified pipe project planning ............
  • Page 225 Aspirating smoke detector VENTUM PRO LITE List of figures Image 71 Mounting orientation ......................122 Image 72 Drilling intervals for bottom section of housing ..............123 Image 73 Device brackets ....................... 124 Image 74 Drill hole intervals [mm] for bracket type MT-1 ..............124 Image 75 Opening the device......................
  • Page 226 List of figures Aspirating smoke detector VENTUM PRO LITE Image 96 Position of the reset circuit board ..................144 Image 97 Inserting the termination resistor in the reset circuit board ..........146 Image 98 Mounting plate with reset circuit board ................146 Image 99 Opening the device......................
  • Page 227 Aspirating smoke detector VENTUM PRO LITE List of figures Image 121 Detection of supply and exhaust air openings, e.g. air grille ........... 173 Image 122 Position the aspiration apertures according to the exhaust airflow speed ...... 174 Image 123 Detection in the bypass ....................175 Image 124 Air filter type LF-VE and LF-VE-x ..................
  • Page 228 List of figures Aspirating smoke detector VENTUM PRO LITE Image 146 Detector module LED ...................... 207 Image 147 Manual air purge system with metal 3-way ball valve ............. 209 Image 148 Manual air purge system with 3-way ball valve made of ABS or PVC ......211 Image 149 Replacing the detector modules ..................
  • Page 229: List Of Tables

    Aspirating smoke detector VENTUM PRO LITE List of tables List of tables Table 1 Overview of displays and connections ................Table 2 Air filter – type and areas of application ................Table 3 Special filter (air filter) – type and areas of application ............
  • Page 230 List of tables Aspirating smoke detector VENTUM PRO LITE Table 24 Limit values for project planning with single hole monitoring (I-pipe system) ....Table 25 Diameter of the sampling points for single hole monitoring (I-pipe system) ...... Table 26 Threshold values for project planning with single hole monitoring (I-pipe system) ...
  • Page 231 Aspirating smoke detector VENTUM PRO LITE List of tables Table 48 Diameter of the aspiration apertures for M-pipe system with acceleration openings ..105 Table 49 Diameter of the aspiration apertures for double U-pipe system with acceleration open- ings ............................. 106 Table 50 Overview of low-speed and high-speed systems ..............
  • Page 232: Glossary

    Glossary Aspirating smoke detector VENTUM PRO LITE Glossary Aerosol Aspirating smoke detector Airborne particles in microscopic or sub- Active system, in which the vacuum that is microscopic grain size range. They exist of required for the aspiration of the air samples is unburned parts of the burning material, generated by a system-integrated fan.
  • Page 233 Aspirating smoke detector VENTUM PRO LITE Glossary Detector module Disturbance variable Modular scattered light smoke detectors, All exogenous variables which impair the optimised for use in aspirating smoke detectors intended function of a fire alarm system. with special air supply; with Flow Init button for...
  • Page 234 Glossary Aspirating smoke detector VENTUM PRO LITE parameters, whereby a disturbance variable is Sensitivity detected, thus preventing false alarm. A measure of the fire sensitivity. It is measured in the percentage of light obscuration per Monitoring area metre. The sensitivity (main alarm) is the...
  • Page 235: Annex

    Aspirating smoke detector VENTUM PRO LITE | Annex Annex Related documents ▪ "Air pressure correction tables" (Resources/pdf/9007200091164555.pdf) ▪ "Project planning tables with air filters" (Re- sources/pdf/9007200114838155.pdf) ▪ "Project planning tables with acceleration openings and air filters" (Re- sources/pdf/9007200114835211.pdf) ▪ "Test record" (Resources/pdf/9007199990375563.pdf)
  • Page 236 Air pressure correction table for adjustment Equipment protection Height Air pressure [hPa] at a height of [m above sea level] 1003 1008 1013 1018 1023 1028 1033 1038 1043 1002 1007 1012 1017 1022 1027 1032 1037 1001 1006 1011 1016 1021 1026 1031 1004 1009 1014 1019 1024 1003 1008 1013 1018 1002 1007 1012...
  • Page 237 Air pressure correction table for adjustment Room protection (I-shaped pipe system) Height Air pressure [hPa] at a height of [m above sea level] 1003 1008 1013 1018 1023 1028 1033 1038 1043 1002 1007 1012 1017 1022 1027 1032 1037 1001 1006 1011 1016 1021 1026 1031 1004 1009 1014 1019 1024 1003 1008 1013 1018...
  • Page 238 Air pressure correction table for adjustment Room protection (U-shaped, M-shaped and double U-shaped pipe system) Height Air pressure [hPa] at a height of [m above sea level] 1003 1008 1013 1018 1023 1028 1033 1038 1043 1002 1007 1012 1017 1022 1027 1032 1037 1001 1006 1011 1016 1021 1026 1031 1004 1009 1014 1019 1024 1003 1008 1013 1018...
  • Page 239 Classification VENTUM PRO LITE / PRO LITE-LSNi With acceleration openings and without air filters or with air filters type LF-VE-k Number of aspiration apertures Sensitivity Module [% light obs./ft] 0,015 0,03 0,06 0,12 Number of aspiration apertures Fan voltage Pipe shape Without pipe accessories ≥...
  • Page 240 Classification VENTUM PRO LITE / PRO LITE-LSNi With acceleration openings and air filters type LF-VE Number of aspiration apertures Sensitivity Module [% light obs./ft] 0,015 0,03 0,06 0,12 Number of aspiration apertures Fan voltage Pipe shape Without pipe accessories ≥ 9 ≥...
  • Page 241 Classification VENTUM PRO LITE / PRO LITE-LSNi With acceleration openings and air filters type LF-VE-1 Number of aspiration apertures Sensitivity Module [% light obs./ft] 0,015 0,03 0,06 0,12 Number of aspiration apertures Fan voltage Pipe shape Without pipe accessories ≥ 9 ≥...
  • Page 242 Classification VENTUM PRO LITE / PRO LITE-LSNi With acceleration openings and air filters type LF-VE-2 Number of aspiration apertures Sensitivity Module [% light obs./ft] 0,015 0,03 0,06 0,12 Number of aspiration apertures Fan voltage Pipe shape Without pipe accessories ≥ 9 ≥...
  • Page 243 Classification VENTUM PRO LITE / PRO LITE-LSNi With acceleration openings and air filters type SF-400 / SF-650 Number of aspiration apertures Sensitivity Module [% light obs./ft] 0,015 0,03 0,06 0,12 Number of aspiration apertures Fan voltage Pipe shape Without pipe accessories ≥...
  • Page 244 Classification VENTUM PRO LITE / PRO LITE-LSNi Project planning without air filters or with air filters type LF-VE-k Number of aspiration apertures Sensitivity Module [% light obs./m] 0,015 0,03 0,06 0,12 Number of aspiration apertures Fan voltage Pipe shape Without pipe accessories ≥...
  • Page 245 Classification VENTUM PRO LITE / PRO LITE-LSNi Project planning with air filters type LF-VE Number of aspiration apertures Sensitivity Module [% light obs./m] 0,015 0,03 0,06 0,12 Number of aspiration apertures Fan voltage Pipe shape Without pipe accessories ≥ 9 ≥...
  • Page 246 Classification VENTUM PRO LITE / PRO LITE-LSNi Project planning with air filters type LF-VE-1 Number of aspiration apertures Sensitivity Module [% light obs./m] 0,015 0,03 0,06 0,12 Number of aspiration apertures Fan voltage Pipe shape Without pipe accessories ≥ 9 ≥...
  • Page 247 Classification VENTUM PRO LITE / PRO LITE-LSNi Project planning with air filters type LF-VE-2 Number of aspiration apertures Sensitivity Module [% light obs./m] 0,015 0,03 0,06 0,12 Number of aspiration apertures Fan voltage Pipe shape Without pipe accessories ≥ 9 ≥...
  • Page 248 Classification VENTUM PRO LITE / PRO LITE-LSNi Project planning with air filters type SF-400/SF-650 Number of aspiration apertures Sensitivity Module [% light obs./m] 0,015 0,03 0,06 0,12 Number of aspiration apertures Fan voltage Pipe shape Without pipe accessories ≥ 9 ≥...
  • Page 249 Test record VENTUM PRO LITE and PRO LITE TWO Device identification Device number Serial number basic device Serial number detector module Measuring an adjustment values Commissioning (✓/ –) Visual check Depression [Pa] Sensitivity (main alarm) [% light obs./m] Alarm delay...
  • Page 250 IK-E291-003-GB...