00. CONTENT 01. SAFETY INSTRUCTIONS INDEX This product is certified in accordance with European Community 01. SAFETY INSTRUCTIONS (EC) safety standards. This product complies with Directive 2011/65/EU of the European 02. AUTOMATISM Parliament and of the Council, of 8 June 2011, on the restriction TECHNICAL CHARACTERISTICS of the use of certain hazardous substances in electrical and COMPATIBLE COMPONENTS...
01. SAFETY INSTRUCTIONS GENERAL WARNINGS • Children shouldn’t play with the product or opening devices to avoid the motorized door or gate from being triggered involuntarily. • This manual contains very important safety and usage information. • If the power cable is damaged, it must be replaced by the Read all instructions carefully before beginning the installation/ manufacturer, after-sales service or similarly qualified personnel usage procedures and keep this manual in a safe place that it can...
01. SAFETY INSTRUCTIONS the power supply cable. Please note that all the cables must enter conditions have been met. the control board from the bottom. • In the event of tripping of circuits breakers of fuse failure, locate • If the automatism is to be installed at a height of more than 2,5m the malfunction and solve it before resetting the circuit breaker or from the ground or other level of access, the minimum safety and replacing the fuse.
100% working cycle. • MF30 photocells TURBO offers an extendable boom that can change the opening time with different lengths, as well as accessories suitable for different purposes, for example, LED lighting on the boom and safety devices.
02. AUTOMATISM 03. INSTALLATION DIMENSIONS INSTALLATION AND ADJUSTING PROCESS To correctly install the barrier, follow the steps below in the order in which they are found. INSTALLATION AND MECHANICAL ADJUSTMENT OF THE BARRIER • DESCRIPTION PAGE 01 • Build the foundation and fix the structure. 02 •...
02. AUTOMATISM 03. INSTALLATION DOOR OPENING AUTOMATION INSTALLATION CREATE FOUNDATION • Under no circumstances should you place your hands on any component of the barrier when Make a hole measuring 350x460mm and the automation is connected to the power supply. 400mm (or greater) deep to create the fixing foundation.
03. INSTALLATION 03. INSTALLATION POWER CABLE BOOM ASSEMBLY *The barrier structure has guides on the inside through which the barrier wiring must pass in *If you order the barrier without specifying the position of the boom, it will be mounted on an organized manner to the top of the barrier.
03. INSTALLATION FIX BOOM SUPPORTS (OPTIONAL) SET EXTENSIBLE BOOM LENGTH ADJUST THE HEIGHT OF THE SUPPORT (FIXED) • • Start by establishing the length of the boom so you can then place the support, as seen in the image below. If the height of the support arm is not adjusted to the height of The boom must exceed the position of the support arm by 50mm.
03. INSTALLATION 03. INSTALLATION REVERSE BOOM POSITION CHANGE FROM 2 SPRINGS TO 1 If, due to the size of your boom, there is a need to remove a spring, proceed as follows: Unscrew the spring joint bearing and the spring nuts (next to the spring support plate) Release the retaining ring for linkage rod and spring lever...
03. INSTALLATION ADJUST THE SPRING Before adjusting the spring, manually place the boom in a vertical position so that the springs are in the Hold the threaded rod with pliers to approximately 5mm away from the stopper. prevent it from rotating, and tighten position of least tension, and move the connecting rod the adjusting nut until the spring is stretched to the distance mentioned in...
Page 13
03. INSTALLATION 03. INSTALLATION TEST SPRING ADJUSTMENT TUNING TABLE Boom Length 2500 3000 3500 4000 4500 5000 5500 6000 You must turn the motor crank until it stops the counter-cycle and you can move the boom by hand. Opening time (seconds) Parameter P2-SO Parameter P2-SC Quantity of springs...
04. CONNECTIONS CONNECTION DIAGRAM • MicroSwitch • Photocells • Led strip • Power supply 5Vdc⎓ | 7.5W • 8K2 Safety edge If using Safety edge, you must activate the Safety edge input: Menu → → • Encoder • Power • Motor supply 12Vdc⎓...
04. CONNECTIONS 04. CONNECTIONS CONNECTION DIAGRAM - MASTER / SLAVE (OPTIONAL) CONNECTION DIAGRAM - MM90-RGB MODULE (OPTIONAL) MENU MENU • MM90-RS485 Module V+ Y R + R G B + R G B +12V- +12V- LS FO FC LE LA LB LS FO FC SEC 2 SEC 1...
05. TROUBLESHOOTING INSTRUCTIONS FOR END CONSUMERS / SPECIALIZED TECHNICIANS Anomaly Procedure Behavior Procedure II Discovering the origin of the problem ⎓ 1 • Open the barrier door; 2 • Measure the 24Vdc output of the transformer to detect the location of the fault; ⎓...
06. MAINTENANCE MAINTENANCE TASKS AND FREQUENCY During maintenance/revision check the parameters mentioned below. On the date you carry out the maintenance, mark with an "X" the tasks performed. Maintenance must be carried out by a specialized technician as regularly as indicated. Frequency Date Date...