1.Installation Precautions Please follow the equipment installation steps process to ensure the The definition of each interface must be clear during the installation process, Flow chart of installation steps: Schematic diagram of battery interface: equipment can be successfully installed. otherwise the wrong connection will lead to installation failure or even damage to the equipment.
2.Check the Packing List Please refer to the packing items shown below, please check the packing list carefully, if any items are missing, please contact your dealer directly. Power cable 1/Black Power cable 2/Red Battery Wall mount bracket Power cable 4/Red Power cable 3/Black RS485 communication line CAN communication line...
Step 2 : Installation Tools: tools needed in the process of installing equipment, more effective to improve installation efficiency. Phillips screw driver Torque screw driver Hammer 锤子 Marker pen Electric driver Ruler 4.Battery Pack Installation ● Power cable specification: The matching power cable is 4AWG, and the max carrying capacity is 90A. Please do not work under the condition of exceeding this Attention should be paid to the following items before installation: current.
Fit the expansion tubes into the holes, pull them tight, Step 2: Fix the wall mount bracket and then use the expansion screws (packaged with expansion tube for use) to install and secure the wall mount bracket to the wall. There is a hook design on the back of the batterybox.
Analogy derivation, more than two battery connections, connect the negative poles (P- terminal) between the battery packs and connect the positive poles (P+ Step 3: Power connections of more than two batteries terminal) between the battery packs. After the battery is connected according to Steps 1-2, connect the negative pole (P- terminal) of the battery pack A and the BAT- terminal of the inverter with the Step 4: Connect the battery to the inverter power supply power cable 3;...
Page 7
The connection between the inverter and the battery must be connected to the NOTE : CAN communication port of the battery, otherwise communication cannot be performed; similarly, the connection between the batteries must be connected to the RS485 port. 7. Protective Enclosure Installation After all wiring harnesses are connected, insert the protective enclosure from bottom to top as shown in the figure below until the bottom of the enclosure is parallel to the bottom of the battery.
Page 8
The default CAN and RS485 communication protocol for the battery is the Hanchu ESS protocol. Step 2 : Inverter Protocol Selection: Protocol Selection: 1) Check which protocols are supported by the inverter;...