PLANNING YOUR INSTALLATION

Typ.
PLACEMENT OF THE TRC1200
The TRC1200 is designed for installation indoors. Select a location that is central to the inside duct runs,
and close to both the exhaust duct (to the outside) and the Supply Air duct (from the outside). The unit
VIEW
can be installed in any orientation but the contractor is responsible for safe installation of the unit.
3/4"
erall
OA
RA
Pressure
Ports (4) Typ.
terlocked
nect Switch
1 1/8" Typ.
NT VIEW
®
OA: Outside Air intake
RA: Room Air to be exhausted
FA: Fresh Air to inside
INSTALLATION ORIENTATION
Unit may be installed in any
orientation.
NOTE
1. UNLESS OTHERWISE SPECIFIED,
DIMENSIONS ARE ROUNDED TO THE
NEAREST EIGHTH OF AN INCH.
2. SPECIFICATIONS MAY BE SUBJECT
TO CHANGE WITHOUT NOTICE.
3. MIN. DUCT CLEARANCE
FROM DAMPER BLADE WHEN FULLY
OPENED TO BE 2". SMACNA RULES
APPLY.
20 1/8"Minimum
Service Area
(Doors can be
Removed from Hinges.)
Door
Swing
Door
Swing
24 1/2"
18" X 18"
Duct
Receiving
Flange Typ.
RIGHT VIEW
FIGURE F1 SERVICE AREA TRC1200
TRC1200
32"
6"
6 3/8" Typ.
SOLERPALAU-USA.COM INSTALLATION, OPERATION AND MAINTENANCE MANUAL
INSTALLATION
ERV
5

Advertisement

loading
Need help?

Need help?

Do you have a question about the TRC1200 and is the answer not in the manual?

Questions and answers