Page 2
The products covered by this instruction manual are manufactured and/or sold by Vertiv. This document is the property of Vertiv and contains confidential and proprietary information owned by Vertiv. Any copying, use, or disclosure of it without the written permission of Vertiv is strictly prohibited.
• If the PowerBar iMPB will not be installed immediately upon delivery, it should be stored in a clean, dry area with temperatures maintained in the range of 32 °F to 104 °F (0 °C to 40 °C) and humidity of up to 95% Non- Condensing.
Vertiv™ PowerBar iMPB Installer/User Guide 2.1 Power Feed Box The Power Feed Box is an IP2X enclosure that provides connections for incoming power cables to the PowerBar iMPB. The Power Feed Box is usually the first component to be mounted on a run.
(horizontally) or on its edge (vertically). NOTE: Vertiv recommends that the hanging brackets be mounted no more than 30 in. (762 mm) from the center of the joint packs and no more than 60 in. (1,524 mm) apart.
2.3 Busway Track The PowerBar iMPB system allows you to supply electrical power to other parts of the building using busway systems connected together. Busway track pieces must be connected to another track piece, an End Cap or a Joint Pack in order to complete an installation.
The tap-off conductors can be inserted into the busway track while ensuring that no conductors are exposed to the installer. The PowerBar iMPB housing, earth strip and mechanical housing ensure that the Tap-Off Box cannot be inserted in the wrong orientation with reverse polarity.
To Install the End Cap: Remove the two Pan head screws from the End Piece using a P3 screwdriver. 2. Remove the End Piece from the PowerBar iMPB. 3. Install the busway End Cap in place of the end cap.
Follow the Inspection and Startup Checklist on page 35 when installing the busway system. A qualified electrician should be employed to perform the equipment inspection and startup. System startup may be arranged by calling your local Vertiv sales representative or Vertiv. •...
4 Operating Instructions 4.1 Startup Procedures Before the PowerBar iMPB is placed in service after initial installation, after equipment relocation or after equipment has been de-energized for an extended period of time, perform equipment inspection and startup procedures as detailed in...
5 Maintenance The design of the PowerBar iMPB lends itself to simple, reliable installation that enables future modifications to be carried out easily. It has no defined routine maintenance requirements. Any maintenance that may be required is easily identified by thermal imaging of the run.
Appendix B: Inspection and Startup Checklist A copy of the appropriate checklist (furnished with the equipment) must be completed, signed, dated and returned to Vertiv. Warranty coverage of the equipment is not effective unless the checklist is received by the factory.
Appendix C: Submittal Drawings The submittal drawings are in the order of document part number (DPN). Submittal Drawings Contents below groups the drawings by topic/application. NOTE: See SL-71013 Vertiv™ iMPB Submittals addendum document. Table 5.2 Submittal Drawings Contents Document Number Title IMPB BUSBAR...