Connecting cables to the PDU for a 1+1 UPS2000-G-15 kVA/20 kVA parallel system (single-phase input single-phase
output)
 Torque for tightening power cables
Device
UPS2000-G-15 kVA
UPS2000-G-20 kVA
PDU
 Cable list
1. The table lists only the cables directly connected to the PDU. For details about other cables and cable types, see
the quick installation guides for related devices.
2. Configure colors for the cables prepared onsite in accordance with the local regulations.
3. If customers purchase input and output power cables by themselves, use the cables that comply with standards
proposed by Underwriters Laboratories (UL) or International Electrotechnical Commission (IEC).
No.
Item
PDU AC
1
output power
cable
PDU bypass
2
input power
cable
PDU UPS 1
3
AC input
power cable
PDU UPS 1
4
AC output
power cable
PDU UPS 2
5
AC input
power cable
PDU UPS 2
6
AC output
power cable
Tool
Torque
screwdriver
Appearance
Screw
Torque
M5 x 0.8p
1.5 N· m
M5 x 0.8p
1.5 N· m
M5 x 0.8p
1.5 N· m
Specifications
16 mm² (1+1
UPS2000-G-15
kVA/20 kVA parallel
system)
16 mm² (1+1
UPS2000-G-15
kVA/20 kVA parallel
system)
N/A
N/A
N/A
N/A
13
Remarks
Prepared onsite
Prepared onsite
The cables is
delivered with
PDU, with a part
number of
04090676.