Trane S8B1A040M3PSC Installation, Operation And Maintenance Manual page 36

Upflow/downflow/horizontal gas-fired, 1–stage and 2–stage induced draft furnaces with high efficiency motor
Hide thumbs Also See for S8B1A040M3PSC:
Table of Contents

Advertisement

F F u u r r n n a a c c e e G G e e n n e e r r a a l l I I n n s s t t a a l l l l a a t t i i o o n n
Important: A BAYBASE is required when installing the furnace on a combustible floor.
I I n n s s t t a a l l l l a a t t i i o o n n I I n n s s t t r r u u c c t t i i o o n n s s
1. Bend furnace flanges up.
2. Bend furnace side flanges down.
3. Set the coil on top of the furnace.
4. Support the furnace and coil independently.
36
Horizontal Right and Downflow Furnace — no Coil
Refer to
Step
1.,
Step
6.,
Step 7.
5. Screw through the coil cabinet into the furnace
flange. Guide holes are located on the coil.
6. Attach ducting.
7. Seal per local codes and requirements.