GE GL317D Instruction Manual page 75

Sf6 circuit- breaker
Table of Contents

Advertisement

Preparing the breaking chambers
Removing the
chamber casing
Rotating
the chambers
03- 2017
Installation
Chamber - Column Coupling
Remove the side panels and cover from the case.
Using two flexible slings, swing the chambers through 180 then level the
transport covers.
NOTE:
Turn the breaking chamber casing (2) so that the face
with the two 'humps' is facing the lifting equipment.
GE Information
2
L31- 7142EN/02