First Time Start-Up - York YCIV0157 Installation Operation & Maintenance

Air-cooled screw liquid chillers
Table of Contents

Advertisement

Section 5 - Commissioning
Grounding
Verify that the unit's protective ground terminal(s) are
properly connected to a suitable grounding point. En-
sure that all unit internal ground connections are tight.
Water system
Verify the chilled liquid system has been installed cor-
rectly, and has been commissioned with the correct
direction of water flow through the cooler. The inlet
should be at the refrigerant piping connection end of
the cooler. Purge air from the top of the cooler using
the plugged air vent mounted on the top of the cooler
body.
Flow rates and pressure drops must be within the limits
given in Section 6 - Technical data. Operation outside
of these limits is undesirable and could cause damage.
If mains power must be switched OFF for extended
maintenance or an extended shutdown period, the com-
pressor suction, discharge and economizer service stop
valves should be closed (clockwise). If there is a pos-
sibility of liquid freezing due to low ambient tempera-
tures, the coolers should be drained or power should
be applied to the chiller. This will allow the cooler
heater to protect the cooler from freezing down to
- 20°F. Before placing the unit back in service, valves
should be opened and power must be switched on (if
power is removed for more than 8 hours) for at least 8
hours (24 hours if ambient temperature is below 86°F
[30°C]) before the unit is restarted.
Flow switch
Verify a chilled water flow switch is correctly fitted in
the customer's piping on the cooler outlet, and wired
into the control panel correctly using shielded cable.
There should be a straight run of at least five pipe di-
ameters on either side of the flow switch. The flow
switch should be connected to Terminals 2 and 13 in
the panel.
Temperature sensor(s)
Ensure the leaving liquid temperature sensor is coated
with heat conductive compound (Part No. 013-00890-
000) and is inserted to the bottom of the water outlet
sensor well in the evaporator. This sensor is part of the
pump control freeze protection operation. It provides
some freeze protection and must always be fully in-
serted in the water outlet sensor well.
46
Programmed options
Verify that the options factory-programmed into the
Micro Panel are in accordance with the customer's
order requirements by pressing the OPTIONS key on
the keypad and reading the settings from the display.
Programmed settings
Ensure the system cutout and operational settings are in
accordance with the operating requirements by press-
ing the PROGRAM key.
Date and time
Program the date and time by first ensuring that the
CLK jumper JP2 on the chiller control board is in the
ON position. See Figure 79 on page 170 and Figure
80 on page 171. Then press the DATE/TIME key and
set the date and time (see Page 270).
Start/stop schedule
Program the daily and holiday start/stop by pressing
the SCHEDULE key (see Page 270).
Setpoint and remote offset
Set the required leaving chilled liquid temperature
setpoint and Control Range under the SETPOINTS
key. The chilled liquid temperature control settings
need to be set according to the required operating con-
ditions.
If remote temperature reset (offset) is to be used, the
maximum reset required must be programmed by
pressing the SETPOINTS key (see Page 262).

First time start-up

During the commissioning period there
should be sufficient heat load to run the
unit under stable full load operation
to enable the unit controls, and system
operation to be set up correctly, and a
commissioning log taken. Be sure that
the chiller is properly programmed and
the Equipment Pre Start-up and Start-up
Checklist (Page 56) is completed.
Interlocks
Verify that liquid is flowing through the cooler and that
heat load is present. Ensure that any remote run inter-
locks are in the run position and that the Daily Sched-
ule requires the unit to run or is overridden.
Form 201.23-NM2
Issue date: 12/19/2023
Johnson Controls

Advertisement

Table of Contents
loading

Table of Contents