Advertisement

Quick Links

SERVICE POLICY & PROCEDURES
PREPaRatIOn
Commissioning of this unit should only
be carried out by Johnson Controls
Authorized personnel.
Commissioning personnel should be thoroughly familiar
with the information contained in this literature.
Perform the commissioning using the detailed checks
outlined in the EQUIPMENT START-UP CHECK as
the commissioning procedure is carried out.
PREPaRatIOn – gEnERaL
The following basic checks should be made with the
customer power to the unit switched OFF.
Proper electrical lock out and tag pro-
cedures must be followed.
Inspection
Inspect unit for installation damage. If found, take
action and/or repair as appropriate.
Refrigerant Charge
Packaged units are normally shipped as standard with a
full refrigerant operating charge. Check that refrigerant
pressure is present in both systems and that no leaks
are apparent. If no pressure is present, a leak test
must be undertaken, the leak(s) located and repaired.
Remote systems and units are supplied with a nitrogen
holding charge. These systems must be evacuated with
a suitable vacuum pump/recovery unit as appropriate
to below 500 microns.
0590-1500 50Hz & 0157-0397 60Hz
StaRt-UP CHECkLISt
Supersedes: Nothing
COmmISSIOnIng
Do not liquid charge with static water in the cooler.
Care must also be taken to liquid charge slowly to avoid
excessive thermal stress at the charging point. Once the
vacuum is broken, charge into the condenser coils with
the full operating charge as given in the Technical Data
Section.
Service and Oil Line Valves
Open each compressor suction, economizer, and
discharge service valve. If valves are of the back-seat
type, open them fully (counterclockwise) then close one
turn of the stem to ensure operating pressure is fed to
pressure transducers. Open the liquid line service valve
and oil return line ball valve fully in each system.
Compressor Oil
To add oil to a circuit - connect a YORK hand oil pump
(Part No. 470-10654-000) to the 1/4" oil charging
valve on the oil separator piping with a length of clean
hose or copper line, but do not tighten the flare nut.
Using clean oil of the correct type ("L" oil), pump
oil until all air has been purged from the hose then
tighten the nut. Stroke the oil pump to add oil to the oil
system. The oil level should be between the middle of
the lower and middle of the upper sight glasses of the
oil separator. Approximately 4-5 gallons is present in
the each refrigerant system, with typically 1-2 gallons
in each oil separator. Oil levels in the oil separators
above the top sight glass in either oil separator should
be avoided and may cause excessive oil carryover
in the system. High oil concentration in the system
may cause nuisance trips resulting from incorrect
readings on the level sensor and temperature sensors.
Temperature sensor errors may result in poor liquid
control and resultant liquid overfeed and subsequent
damage to the compressor.
Fans
Check that all fans are free to rotate and are not
damaged. Ensure blades are at the same height when
rotated. Ensure fan guards are securely fixed.
YCIV
Form 201.23-CL1 (309)

Advertisement

Table of Contents
loading

Summary of Contents for York YCIV 0590-1500 50Hz

  • Page 1 Compressor Oil PREPaRatIOn – gEnERaL To add oil to a circuit - connect a YORK hand oil pump (Part No. 470-10654-000) to the 1/4” oil charging The following basic checks should be made with the valve on the oil separator piping with a length of clean customer power to the unit switched OFF.
  • Page 2 FORM 201.23-CL1 (309) Isolation / Protection Flow Switch Verify all sources of electrical supply to the unit Verify a chilled water flow switch is correctly fitted in are taken from a single point of isolation. Check the customer’s piping on the cooler outlet, and wired that the maximum recommended fuse sizes given into the control panel correctly using shielded cable.
  • Page 3: First-Time Startup

    FORM 201.23-CL1 (309) FIRSt tImE StaRt-UP Refrigerant Flow When a compressor starts, a flow of liquid refrigerant During the commissioning period there will be seen in the liquid line sight glass. After several should be sufficient heat load to run the minutes of operation, and provided a full charge of unit under stable full load operation refrigerant is in the system, the bubbles will disappear...
  • Page 4 FORM 201.23-CL1 (309) Subcooling Check liquid subcooling at steady full compressor load only. It is important that all fans are running for the system. Measure liquid line temperature on the copper line at the main liquid line service valve. Measure liquid pressure at the liquid line service valve. Subcooling should be 5 - 7°F (2.77 - 3.88°C).
  • Page 5: Equipment Start-Up Check Sheet

    FORM 201.23-CL1 (309) EqUIPmEnt StaRt-UP CHECk SHEEt UnIt CHECkS (nO POWER) JOB NAME: _____________________________ The following basic checks should be made with the customer power to the unit switched off. SALES ORDER #: ________________________ Proper electrical lock out and tag pro- LOCATION: _____________________________ cedures must be followed.
  • Page 6 In the unlikely event it is necessary to add oil, con- 15. Check to assure the remote start/stop for Sys #1 nect a YORK oil pump to the charging valve on the on Terminals 2 to 15 and Sys #2 on Terminals 2 to...
  • Page 7: Panel Checks

    3. Verify the control panel display is illuminated. 8. Press the STATUS Key. If the following message 4. To prevent the compressors from starting, assure appears, immediately contact YORK Product that the system switches under the SYSTEM Technical Support. The appearance of this message SWITCHES key are in the OFF position.
  • Page 8: Chilled Liquid Setpoint

    FORM 201.23-CL1 (309) If the following message appears when the STATUS PROgRammED VaLUES key is pressed, immediately contact YORK Product 10. Program the required operating values into the Technical Support. The appearance of this mes- micro for cutouts, safeties, etc. and record them in sage indicates the chiller is a HIGH IPLV chiller the chart below.
  • Page 9: Initial Start-Up

    FORM 201.23-CL1 (309) DatE/tImE, DaILY SCHEDULE, anD CLOCk CHECkIng SUBCOOLIng anD SUPERHEat JUmPER The subcooling should always be checked when charging the system with refrigerant and/or before 12. Set the Date and Time. checking the superheat. The subcooling measurement 13. Program the Daily Schedule start and stop times. should always be taken with the system loaded, the 14.
  • Page 10: Leak Checking

    FORM 201.23-CL1 (309) SUBCOOLIng SUPERHEat Example: Example: Liquid line pressure = Suction Temp = 46°F (8°C) 110 PSIG converted to 93°F (33.9°C) minus Suction Press Minus liquid line temp. -87°F (30.6°C) 30 PSIG converted to Temp - 35°F (1°C) SUBCOOLING = 6°F (3.3°C) 11°F (6°C) The suction temperature should be taken 6”...
  • Page 11 FORM 201.23-CL1 (309) nOtES JOHNSON CONTROLS...
  • Page 12 P.O. Box 1592, York, Pennsylvania USA 17405-1592 Tele. 800-861-1001 Subject to change without notice. Printed in USA Copyright © by Johnson Controls 2009 www.york.com ALL RIGHTS RESERVED Form 201.23-CL1 (309) Supersedes: Nothing...

This manual is also suitable for:

Yciv 0157-0397 60hz

Table of Contents