Inner Flue Support Bracket
Flue Elbow
Fig. 29
© Baxi Heating UK Ltd 2006
Fig. 28
Flue
Apply Lubricant for ease
of assembly. Ensure Flue
is fully engaged into Flue
Elbow
Gasket
Flue Trim
8.0 Installation
8.7
Fitting the Flue (Cont)
6. Ensure the inner flue support bracket is positioned in
the flue (Fig. 28).
7. Engage the flue into the flue elbow using soap solution
to ease the engagement ensuring the flue is assembled as
shown (Fig. 29).
8. Place the gasket over the flue exit on the boiler.
9. Slide the flue assembly through the hole in the wall.
10. Engage the elbow on to the flue connection on top
of the boiler. Secure with the four screws supplied in the
kit.
11. Make good between the wall and air duct outside the
building ensuring the 3° drop between the terminal and
elbow.
12. The flue trim should be fitted once the installation is
complete and the flue secure (Fig. 30). Apply a suitable
mastic to the inside of the trim and press against the wall
finish, making sure the brickwork is dust free and dry.
13. If necessary fit a terminal guard (see Section 7.9).
VERTICAL FLUEING
1. Only a flue approved with the Baxi Platinum 15 and 24
HE can be used.
2. For information on vertical flues consult the Baxi Flue
Guide Brochure or Notes for Guidance supplied with the
vertical flue pack.