Test operation
1. Preparation of test operation
•
The client approves the air conditioner.
•
Specify the important notes for air conditioner to the client.
2. Method of test operation
•
Put through the power, press ON/OFF button on the remote
controller to start operation.
•
Press MODE button to select AUTO, COOL, DRY , normal or not.
•
FAN and HEAT to check whether the operation is If the ambient
temperature is lower than 16 , the air conditioner can't start
cooling.
CONFIGURATION OF CONNECTION PIPE
1. Standard length of connection pipe: 5m, 7.5m, 8m.
2. Min. length of connection pipe.
For the unit with standard connection pipe of 5m, there is no
limitation for the min length of connection pipe. For the unit with
standard connection pipe of 7.5m and 8m, the min length of
connection pipe is 3m.
3. Max. length of connection pipe is shown as below.Step 7: Connect
wire of indoor unit
Max. length of connection pipe
Cooling capacity
5000Btu/h (1465W)
7000Btu/h (2051W)
9000Btu/h (2637W)
12000Btu/h (3516W)
18000Btu/h (5274W)
24000Btu/h (7032W)
28000Btu/h (8204W)
36000Btu/h (10548W)
42000Btu/h (12306W)
48000Btu/h (14064W)
Max. length of
connection pipe(m)
15
15
15
20
25
25
30
30
30
30
47
GB