Mechanical Operations Counter Installation (Optional); Rejection Feature - GE EntelliGuard G Installation, Operation And Maintenance Manual

Hide thumbs Also See for EntelliGuard G:
Table of Contents

Advertisement

EntelliGuard® G Circuit Breaker
Section 7 – Accessories Installation
4.
Connect the wires via the plug connectors to the
respective locations of the secondary isolating
contacts A33, A34 and A35 (Fig. 7.18).
Figure 7.18. Plug Connector Location
5.
Replace the front cover.
6.
Connect the wires via the plug connectors to the
respective locations of the secondary isolating
contacts A33, A34 and A35.
7.
Replace the front cover.
MECHANICAL OPERATIONS COUNTER INSTALLATION
(OPTIONAL)
This device is mounted to the inside of the front cover. It
cannot be reset.
1.
Remove the front cover.
2.
Position the mechanical operations counter (Fig. 7.19)
over the two holes provided inside the cover, ensuring
the indicator face is aligned to show through the
window in the cover.
Figure 7.19. Mechanical Operations Counter Location
A Mechanical operations counter
B Operating arm
C Spring charging link
3.
Ensure the operating arm on the counter rides over the
spring charging link of the circuit breaker mechanism.
4.
Mount in position using the screws provided.
38
Courtesy of store.ips.us

REJECTION FEATURE

This factory-installed, pin and gate device prevents the
insertion of a circuit breaker into a cassette if the nominal
rating of the breaker is incompatible with that of the
cassette and its ancillary equipment. Recommended
configurations are provided with the rejection feature for the
entire EntelliGuard range (Fig. 7.20).
Figure 7.20. Rejection Feature
A Pin block assembly
Fig. 7.21 shows the corresponding restrainer assembly
mounted on the cassette with one M4 nut and lock washer.
There are two of these assemblies, one on each side of the
cassette.
Figure 7.21 Corresponding Restrainer
A
B
C
©2012 General Electric All Rights Reserved
DEH-41304C
13 March 14

Advertisement

Table of Contents
loading

Table of Contents