Prepare The Mating Faces (Im B3); Prepare The Mating Face For A Flange Connection; Prepare The Mating Face For Wall Mounting; Lift The Machine To Where It Will Be Installed, And Position It - Siemens SIMOTICS FD 1LQ1 Operating Instructions Manual

Table of Contents

Advertisement

Assembly

5.3 Lift the machine to where it will be installed, and position it

5.2.4

Prepare the mating faces (IM B3)

● Ensure that the foundation faces are flat and free of contaminations.
● Check the dimensions of the mounting-foot holes.
See also
Service and Support (Page 163)
5.2.5

Prepare the mating face for a flange connection

● Clean the flange before installation, and make sure that the flange face is flat and free of
● Check the geometry of the flange.
5.2.6

Prepare the mating face for wall mounting

● Ensure that the wall surface is flat and free of contaminations.
● Check the dimensions of the mounting-foot holes.
● Support the machine from below, e.g. using a wall bracket or by bolting it.
5.3
Lift the machine to where it will be installed, and position it
5.3.1

Preconditions for correct alignment and secure attachment

Detailed specialist knowledge of the following measures is required in order to correctly align
and securely fit the equipment.
● Preparing the foundation
● Selecting and mounting the coupling
● Measuring the concentricity and axial eccentricity tolerances
● Positioning the machine
If you are not familiar with the prescribed measures and procedures, then you can make use of
the services offered by the local Service Center (Page 163).
54
Note
Shims
To establish a defined mounting surface, you can order shims (option L31) from our Service
Center.
contaminations.
SIMOTICS FD 1LQ1
Operating Instructions 01/2019

Advertisement

Table of Contents
loading

Table of Contents