Power Cable Entry; Field Control Wiring; 24 V Power Reserve For The User - Carrier 30XW-PZE Series Installation, Operation And Maintenance Instructions

Table of Contents

Advertisement

6 - ELECTRICAL CONNECTION
Table of minimum and maximum connectable wire sections.
Connectable
30XW-PZE /
wire section
30XWHPZE -
Circuit(s) A(/B)
Section
mm² (per phase)
Units without option 150
301
1 x 240
401
1 x 240
451
1 x 240
551
1 x 240
601
1 x 240
651
1 x 240
801
2 x 240/2 x 240
901
2 x 240/2 x 240
1001
2 x 240/2 x 240
1101
2 x 240/2 x 240
Units with option 150
301
1 x 240
401
1 x 240
451
1 x 240
551
2 x 240
601
2 x 240
651
2 x 240
801
2 x 240/2 x 240
901
2 x 240/2 x 240
1001
2 x 240/2 x 240
1101
2 x 240/2 x 240
(1)  Connection capacities actually available for each machine, defined according to the connection terminal size, the control box access opening size and the available 
space inside the control box.
(2) Selection simultation result considering the hypothesis indicated.
(3) If the maximum calculated section is for an XLPE cable type, this means that a selection based on a PVC cable type can exceed the connection capacity actually
available. Special attention must be given to the selection.
Note: The currents considered are given for a machine equipped with a hydraulic module operating at maximum current.

5.5 - Power cable entry

The power cables can enter the unit control box from above the
unit. A removable aluminium plate on the upper part of the control
box face allows introduction of the cables. Refer to the certified 
dimensional drawing for the unit.
The plate fixing on the electrical box as well as the cable passage 
through the plate have to be tight.
If  not,  the  differential  pressure  sensor      should  not  detect  the 
electrical box fan operating. This will prevent the unit from starting.

5.6 - Field control wiring

IMPORTANT: Field connection of interface circuits may lead
to safety risks: any control box modification must maintain
equipment conformity with local regulations. Precautions
must be taken to prevent accidental electrical contact between
circuits supplied by different sources:
The routing selection and/or conductor insulation
characteristics must ensure dual electric insulation.
In case of accidental disconnection, conductor fixing between
different conductors and/or in the control box prevents any
contact between the conductor ends and an active energised
part.
Calculation favourable case:
Perforated horizontal conduit (standardised
routing No. 15)
(1)
XLPE insulated cable
Section
Max. length
(2)
mm² (per phase)
m
1 x 50
190
1 x 70
200
1 x 70
175
1 x 95
200
1 x 120
210
1 x 120
200
1 x 70/1 x 70
180/180
1 x 95/1 x 95
230/230
1 x 120/1 x 95
240/230
1 x 120/1 x 120
220/220
1 x 70
200
1 x 95
200
1 x 120
220
1 x 150
210
1 x 185
230
1 x 185
220
1 x 120/1 x 120
250/250
1 x 150/1 x 150
270/270
1 x 185/1 x 150
220/270
1 x 185/1 x 185
220/220
Calculation unfavourable case:
Closed conduit (standardised routing No. 41)
PVC insulated cable, if possible
Section
(2)
Cable type
mm² (per phase)
XLPE Cu
1 x 95
XLPE Cu
1 x 120
XLPE Cu
1 x 150
XLPE Cu
1 x 240
XLPE Cu
1 x 240
XLPE Cu
1 x 240
XLPE Cu
1 x 185/1 x 185
XLPE Cu
1 x 240/1 x 240
XLPE Cu
2 x 150/1 x 185
XLPE Cu
2 x 150/2 x 150
XLPE Cu
1 x 120
XLPE Cu
1 x 185
XLPE Cu
1 x 240
XLPE Cu
2 x 150
XLPE Cu
2 x 185
XLPE Cu
2 x 185
XLPE Cu
2 x 120/2 x 120
XLPE Cu
2 x 150/2 x 120
XLPE Cu
2 x 240/2 x 150
XLPE Cu
2 x 240/2 x 240
 Control manual and the certified wiring 
Refer to the SmartVu
TM
diagram supplied with the unit for the field control wiring of the 
following features:
• Customer interlock
• Remote on/off switch
• Demand limit external switch
• Remote dual set point
• Alarm, alert and operation report
• Evaporator pump control
• Heat reclaim condenser pump control (option)
• Hot water valve control (option)
• Various interlocks on the Energy Management Module
(EMM) board (accessory or option)
CCN bus connection
• The permanent connection to the system CCN bus is made
at the terminal provided for this purpose inside the control
box.
• The connection of the CCN service tool is possible at a
socket under the control box, accessible from outside.
All panel feedthrough of control cables have to be tight to allow
electrical box fan operating detection.

5.7 - 24 V power reserve for the user

Control circuit reserve:
After all required options have been connected, the TC transformer
includes  a  power  reserve  that  can  be  used  for  the  field  control 
wiring: 2 A (24 V a.c.) or 48 VA.
Max. length
Cable type
(3)
m
330
PVC Cu
320
PVC Cu
340
PVC Cu
440
PVC Cu
390
PVC Cu
300
PVC Cu
480/480
PVC Cu
500/500
PVC Cu
500/500
PVC Cu
500/500
PVC Cu
320
PVC Cu
360
PVC Cu
400
PVC Cu
380
PVC Cu
400
PVC Cu
340
PVC Cu
370
PVC Cu
370/370
PVC Cu
380/370
PVC Cu
380/380
PVC Cu
17