4. APsystems Microinverter System Installation
4.3.8 Step 8 - Connect APsystems Microinverters to Grid
①.Please install bi-polar circuit breakers with proper rated current or according to the local regulation,
which are mandatory to connect to grid.
②.Leakage current breakers or AFCI/GFCI breakers are not recommended to install.
4.3.9 Step 9 - AC Extension Cable
Bus Cable End Cap
When AC extension cable is needed, users could connect the AC bus cable and AC extension cable in a junction
box or use a pair of male/female AC connectors that APsystems provides as optional accessory.
AC Extension Cable
Male/Female AC Connectors
APsystems Microinverter QT2 Installation manual
Figure 11
Figure 12