/ Commissioning
DANGER
LOCOUT / TAGOUT
Before set-up, maintenance, service, or repair.
Checklist before commissioning:
All operators follow requirements in for safe work practices and appropriate PPE.
LOCKOUT-listing procedure should be applied properly.
All operators should be trained for NZS maintenance and fully aware of the risk.
5.1 Switch on the Charging system
DANGER
Mortal danger due to electrocution!
The contact with high power parts can result in electric shock, burns or death.
Checklist before switching on:
Visual check if there is any damage or deformation of the product.
Visual inspection of coolant leakage, especially inlet and outlet of air conditioning.
Check if there is trace of condensation inside of charger and battery compartment.
Make sure that the main switch in the middle right hand behind the front door of the NZS
charger is switched off.
It must be ensured that no AC voltage is applied to the mains connections.
It must be ensured that all connections are made correctly.
Insert the mains fuses in distribution box and make sure that the fuse holders are properly
closed.
Please check that the addresses have been set correctly on Power Module M1-M7.