Pumping Down (Re-Installation) - Midea MSV1-07CR-QB8F Service Manual

Table of Contents

Advertisement

service port.
Caution:
If gas leakage is discovered in step (3) above, take the following measures.
If the leaks stop when the piping connections are tightened further, continue working from step
(4).
If the gas leaks do not stop when the connections are retightened, repair the location of the
leak, discharge all of the gas through the service port, and then recharge with the specified
amount of gas from a gas cylinder.

8.5 Pumping down (Re-installation)

Procedure:
1. Confirm that both the 2-way and 3-way valves are set to the opened position.
Remove the valve stem caps and confirm that the valve stems are in the opened position.
Be sure to use a hexagonal wrench to operate the valve stems.
2. Operate the unit for 10 to 15 minutes.
3. Stop operation and wait for 3 minutes, then connect the charge set to the service port of the 3-way
valve.
Connect the charge hose with the push pin to the gas service port.
4. Air purging of the charge hose.
Open the low-pressure valve on the charge set slightly to purge air from the charge hose.
5. Set the 2-way valve to the close position.
6. Operate the air conditioner at the cooling cycle and stop it when the gauge indicates 0.1MPa.
7. Immediately set the 3-way valve to the closed position.
Service manual
- 18 -