Place and fix the cables JA-1/2/3/4/5 and JB-1/2/3/4/5 inside the UPS cabinets in the position
illustrated in the drawing.
NOTE !
Pay attention when cabling and routing the bus cables JA and JB inside the UPS
cabinet.
In case one unit should be removed from the parallel system, the bus cables JA
and JB must be removed from the cabinet without disconnecting them from the
metal plate where the sockets JA and JB are located.
For reliability reasons the cables JA-1/2/3/4/5 and JB-1/2/3/4/5 connecting the units should be run
in separated protected conduits (as indicated in Fig. 3.9.3-3) separated from the power cables.
It is important that the cable JA must be the same length as cable JB.
WARNING !
Connection and commissioning of an additional UPS to an existing parallel system,
must be performed by a GE SERVICE ENGINEER from of your
Modifications reserved
OPM_SGS_ISG_M22_M30_2US_V010.doc
JB
JA
Q1
Q2
1
2
13
1
12
3
2
4
5
7
6
8 9
14 15
16 17
18
19 20
10
21
22
11
3
JB1
1
4
2
3
4
JA1
UPS 1
Fig. 3.9.3-3 Control bus cable routing and connection
JB1
JB
JB2
JA1
JA2
JA
Q1
Q2
1
2
2
13
1
12
4
3
14 15
17
16
6
5
7
9
8
21
22
19 20 10
18
11
3
1
4
2
3
4
UPS 2
JB2
JA2
Service Center.
Page 35/40
Installation Guide SG Series 225 & 300 UL S2

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sg225Sg series

Table of Contents