4. Control unit installation
See figure 2.
Control units must always be installed securely to the plinth with four screws from the corners (1). The
plinth must be installed to the ground according to the instructions on the plinth. Cabinets must be
mounted and used in the position according to the drawing below.
1
Preparations before comissioning:
· Make sure the hydraulic connections are clean.
· Keep all protective caps on the hydraulic connections until hoses are connected. This is for
preventing the system and its components against contamination.
· Check that all bolts and hydraulic couplings are fastened. The control cabinets are always pressure
tested and verified before delivery. However, during delivery, the threaded connections can loosen
and therefore this should be controlled before pressurizing the system.
www.vexve.com
Figure 2. Mounting holes.
7