Cisco NCS 6008 LCC Installing page 27

Advertisement

Installing Power Components
Step 8
If necessary, repeat these steps for all power trays.
Powering On and Powering Off the LCC
This section describes how to power on and power off an AC or DC powered system.
Powering On the LCC
Prerequisites
Note
If you have a DC power system installed, wiring at the Battery Distribution Fuse Bay (BDFB) or at the power
plant should be complete.
Required Tools and Equipment
• Voltmeter
Steps
To power on the LCC, perform the following steps:
Step 1
Make sure that the LCC is properly grounded (see the
Step 2
Make sure that the I/O switches on the rear are in the OFF position.
Installing the LCC Ground Cable
Installing an AC or DC Power Tray (Preinstalled)
Installing an AC or DC Power Module
Installing AC Input Power Cords
Installing DC Input Power Cables
Powering On and Powering Off the LCC
Bonding and Grounding Guidelines, on page
Installing Power Components
1).
27