SECTION 6: COMMISSIONING

Start-Up

Purpose
This section contains the necessary steps required
to prepare the BioShield
operation.
Frequency
Required with new construction, retro-fit or replacement
of outdated equipment.
Parts and Required Equipment
• Personal Protective Equipment
General risk due to pressurized piping and UV
Vessel!
General risk due to electricity!
Hydraulic shock (water hammer) may occur
as a result of improper use of valve(s) or trapped air
inside the vessel. Hydraulic shock and trapped air can
damage the vessel.
Trapped air or no-flow situations may damage
the vessel and/or the UV lamps due to overheating.
BioShield® PRO UV System Installation and User's Guide
PRO UV System for proper
®
Procedure
1. Confirm that all personnel operating this UV system
have thoroughly reviewed these instructions prior to
operating.
2. Remove all dirt/debris from power supply enclosure,
vessel and installation area resulting from installation
activities.
3. Inspect all plumbing connections and immediate
plumbing network to ensure safe start-up.
4. Inspect the vessel's Quartz Sleeve Module Faceplate
to ensure proper assembly.
5. Inspect quartz sleeve assemblies (Quartz Sleeve
Retaining Nuts) confirming that they are tight.
6. Inspect Power Supply Enclosure, confirm that it
has been mounted properly and input power is in
accordance with local ordinances and codes.
7. Verify that a successful Leak Test has been
completed. See Page 13 for instructions.