Please pay attention to the following items when installing multiple modules:
- Each module corresponds to an address code which cannot be repeated.
- Main water outlet temperature sensing bulb, target flow controller and auxiliary electric heater are under control of
the main module.
- One wired controller and one target flow controller are required and connected on the main module.
- The unit can be started up through the wired controller only after all addresses are set and the aforementioned
items are determined. The wire length betweent the wired controller and outdoor unit should be <500m.
8.5.10 Installation of single or multiple
water pumps
1) DIP switch
The choice of DIP switch see Table 8-5 in detail when single or
multiple water pumps are installed for SCV-750EBand
SCV-900EB and SCV-1400EB andSCV-1800EB.
Pay attention to the following problems:
a. If the DIP switch is inconsistent, and the error code is FP, the
unit is not allowed to operate.
b. Only the main unit has the water pump output signal when
single water pump installed, auxiliary units has no water pump
output signal.
c. The water pump control signal is available for both the main
unit and auxiliary units when multiple pumps installed.
2) Installation of water pipe system
a. Single water pump
Piping does not require a one-way valve when single water pump
is installed, refer to figure as follow.
unit
unit (1#)
(n-1#)
inlet water
outlet water
Fig.8-33 Installation of single water pump

9 STRAT-UP AND CONFIGRUATION

9.1 Initial start-up at low outdoor ambient temperatures
During initial start-up and when water temperature is low, it is important that the water is heated gradually. Failure to do so may
result in concrete floors cracking due to rapid temperature change. Please contact the responsible cast concrete building
contractor for further details.
9.2 Points for attention prior to trial run
1) After the water system pipeline is flushed several times, please make sure that the purity of water meets the requirements;
the system is re-filled with water and drained, and the pump is started up, then make sure that water flow and the pressure at
the outlet meet the requirements.
2) The unit is connected to the main power 12 hours before being started up, to supply power to the heating belt and pre-heat
the compressor. Inadequate pre-heating may cause damages to the compressor.
3) Setting of the wired controller. See details of the manual concerning setting contents of the controller, including such basic
Zsettings as refrigerating and heating mode, manual adjustment and automatic adjustment mode and pump mode. Under
normal circumstances, the parameters are set around standard operating conditions for trial run, and extreme working
conditions should be prevented as much as possible.
4) Carefully adjust the target flow controller on the water system or the inlet stop valve of the unit, to make the water flow of the
system be 90% of the water flow specified in troubleshooting table.
CAUTION
unit (0#)
water pump
terminal
Tw
b. Multiple water pumps
Each unit is required to install a one-way valve when multiple
pumps are installed, refer to figure as follow.
unit
unit (1#)
(n-1#)
water pump
inlet water
Fig.8-34 Installation of multiple water pump
3) Electric wiring
Only the main unit requires wiring when single water pump
installed, auxiliary units do not require wiring. All of the main
unit and auxiliary units require wiring when multiple water
pumps installed.For specific wiring, see figure 8-18.
34
unit (0#)
one-way valve
terminal
Tw
outlet water

Advertisement

Table of Contents
loading

This manual is also suitable for:

Scv-750ebScv-1400ebScv-1800eb

Table of Contents