Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation
Guide
First Published: 2019-07-08
Last Modified: 2019-07-08
Americas Headquarters
Cisco Systems, Inc.
170 West Tasman Drive
San Jose, CA 95134-1706
USA
http://www.cisco.com
Tel: 408 526-4000
800 553-NETS (6387)
Fax: 408 527-0883

Advertisement

Table of Contents
loading

Summary of Contents for Cisco Nexus 93360YC-FX2

  • Page 1 Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide First Published: 2019-07-08 Last Modified: 2019-07-08 Americas Headquarters Cisco Systems, Inc. 170 West Tasman Drive San Jose, CA 95134-1706 http://www.cisco.com Tel: 408 526-4000 800 553-NETS (6387) Fax: 408 527-0883...
  • Page 2 Any products and features described herein as in development or available at a future date remain in varying stages of development and will be offered on a when-and if-available basis. Any such product or feature roadmaps are subject to change at the sole discretion of Cisco and Cisco will have no liability for delay in the delivery or failure to deliver any products or feature roadmap items that may be set forth in this document.
  • Page 3: Table Of Contents

    Airflow Requirements Rack and Cabinet Requirements Clearance Requirements C H A P T E R 3 Installing the Chassis Installation Options with Rack-Mount Kits Install a Rack Unpacking and Inspecting a New Switch Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 4 Installing an AC Power Supply Installing an HVAC/HVDC Power Supply Installing a DC Power Supply Connecting a Power Cable to an NXA-PDC-930W Power Supply A P P E N D I X A Rack Specifications Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 5 A P P E N D I X C LEDs Switch Chassis LEDs Fan Module LEDs Power Supply LEDs A P P E N D I X D Additional Kits Rack Mount Kit N9K-C9300-RMK Vent Bracket Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 6 Contents Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 7: Preface

    Braces and a vertical bar within square brackets indicate a required choice within an optional element. Indicates a variable for which you supply values, in context where italics variable cannot be used. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 8: Documentation Feedback

    What's New in Cisco Product Documentation, at: https://www.cisco.com/warp/public/687/Directory/DirTAC.shtml. Subscribe to What's New in Cisco Product Documentation, which lists all new and revised Cisco technical documentation as an RSS feed and delivers content directly to your desktop using a reader application. The RSS feeds are a free service.
  • Page 9: Overview

    • Overview, on page 1 Overview The Cisco Nexus 93360YC-FX2 switch (N9K-C93360YC-FX2) is a 2-rack unit (RU), fixed-port switch designed for spine-leaf-APIC deployment in data centers. This switch has the following ports: • 96 10-/25-Gigabit SFP28 ports • 12 40/100-Gigabit QSFP28 ports •...
  • Page 10 Deployment Scheme for SFP-10G-T-X Transceivers The following figure shows the maximum configuration density of SFP-10G-T-X SFP+ transceivers for this switch. The following figure shows the switch features on the port side of the chassis. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 11 Power supply modules (1 or 2) (AC power supplies shown) with slots numbered 1 (top) and 2 (bottom) Management port (1—RJ-45 copper port) The following figure shows the side of the chassis. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 12 All fan and power supply modules must have the same direction of airflow. Otherwise, the switch can overheat and shut down. If you are installing a dual-direction power supply, that module automatically uses the same airflow direction as the other modules in the switch. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 13 If the switch has port-side exhaust airflow (blue coloring for fan modules), you must locate the ports in the hot aisle. If you locate the air intake in a hot aisle, the switch can overheat and shut down. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 14 Overview Overview Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 15: Preparing The Site

    However, if the switch is located in an unusually humid location, use a dehumidifier to maintain the humidity within an acceptable range. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 16: Altitude Requirements

    Note To predict and prevent strong EMI, you need to consult experts in radio frequency interference (RFI). Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 17: Shock And Vibration Requirements

    The surfaces shall be cleaned and an antioxidant applied before installation. Planning for Power Requirements The switch includes two power supplies (1-to-1 redundancy with current sharing) in one of the following combinations: Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 18 • Ensure that the protective devices are rated not greater than 30A when the switch is powered with regular DC power supplies (rated 48-60VDC). • Ensure that the protective devices are rated not greater than 10A when the switch is powered with HVDC power supplies (rated 240-350VDC). Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 19: Airflow Requirements

    Rack and Cabinet Requirements You can install the following types of racks or cabinets for your switch: • Standard perforated cabinets • Solid-walled cabinets with a roof fan tray (bottom-to-top cooling) Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 20: Clearance Requirements

    Provide the chassis with adequate clearance to route cables, provide airflow, and maintain the switch. For the clearances required for an installation of this chassis in a four-post rack, see the following figure. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 21 19.0 in (43.3 cm) Note Both the front and rear of the chassis must be open to both aisles for airflow. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 22 Preparing the Site Clearance Requirements Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 23: Installing The Chassis

    You can install the switch using the following rack-mount options: • Rack-mount kit (N9K-C9300-RMK) which you can order from Cisco. For four post racks. The rack or cabinet that you use must meet the requirements listed the in...
  • Page 24: Unpacking And Inspecting A New Switch

    • Two power supplies (any combination of the following with the airflow direction being the same as for the fan modules): • fan modules (all fan and power supply modules must have the same airflow direction) • Switch accessory kit Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 25: Planning How To Position The Chassis In The Rack

    Installing the Chassis in a Four-Post Rack Before you install the chassis, be sure that the rack is fully secured to the data center floor. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 26: Installing The Switch Using The N9K-C9300-Rmk Rack-Mount Kit

    • When mounting this unit in a partially filled rack, load the rack from the bottom to the top with the heaviest component at the bottom of the rack. • If the rack is provided with stabilizing devices, install the stabilizers before mounting or servicing the unit in the rack. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 27 2 screws holding one end of the bottom-support 2 screws holding the front end of the bottom-support bracket to the rear of the rack bracket to the front side of the rack Chassis stop on the expanding bottom-support bracket Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 28: Attaching Front-Mount Brackets To The Chassis

    Use two M4 x 6 mm screws to attach the bracket to the chassis. Tighten each screw to 11 to 15 in-lb (1.2 to 1.7 N·m). Step 3 Repeat Steps 1 and 2 to attach the second center-mount bracket to the other side of the chassis. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 29: Installing The Chassis In A Four-Post Rack

    • Make sure that two front-mount brackets are securely fastened to the sides of the chassis at the port end. • Make sure that you have two customer-supplied rack-mount screws (M6 x 10 mm or appropriate screw for the vertical mounting rails on the rack). Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 30 If this happens, press the side rails toward the sides of the chassis so that the chassis stops can go inside the chassis and hold it in place on the rack. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 31: Installing The Airflow Vent Nxa-Acc-Bav4

    (for M6 x 10 mm screws, use 40 in-lbs [4.5 N·m] of torque). Installing the Airflow Vent NXA-ACC-BAV4 The airflow vent bracket (NXA-ACC-BAV4) is required for NEBS (Network Equipment-Building System) compliance. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 32 Holding the vent bracket level, insert screws (12-24 or 10-32, depending on the rack type) in each of the front rack-mount flanges (using a total of two screws) and into the cage nuts or threaded holes in the vertical rack-mounting rails (see item 2 in the following figure). Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 33: Grounding The Chassis

    Insert the stripped end of the grounding wire into the open end of the grounding lug. Use a crimping tool to crimp the lug to the wire, see the following figure. Verify that the ground wire is securely attached to the grounding lug by attempting to pull the wire out of the crimped lug. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 34: Starting The Switch

    • The rack must be close enough to the dedicated power source so that you can connect the switch to the power source by using a designated power cables. • You have the designated power cables for the power supplies that you are connecting to the dedicated power sources. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 35 Turn on the power at the circuit breaker for the DC power source. Step 4 Verify that the power supply LED is on and green. Step 5 Listen for the fans; they should begin operating when the power supply is powered. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 36 A setup utility automatically launches the first time that you access the switch and guides you through the basic configuration. For instructions on how to configure the switch and check module connectivity, see the appropriate Cisco Nexus 9000 Series configuration guide.
  • Page 37: Connecting The Switch To The Aci Fabric

    As shown in the following figure, each APIC is connected to one or two leaf switches and each leaf switch should be connected to every spine switch in the same fabric. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 38: Preparing To Connect To Other Devices

    Cisco equipment. In situations where long parallel cable runs cannot be separated by at least 3.3 feet (1 meter), we recommend that you shield any potential noise sources by housing them in a grounded metallic conduit.
  • Page 39: Connecting Leaf Switches To Apics

    Connecting Leaf Switches to APICs You must downlink one or two (recommended for redundancy) Cisco Nexus 9300 platform ACI-mode leaf switches to each Application Policy Infrastructure Controller (APIC) in your ACI fabric. The type of virtual interface card (VIC) installed on the APIC determines the types of interface cables that you can use to connect the leaf switches to the APICs.
  • Page 40 Connect the other end of the interface cable to a downlink port on a leaf switch. • For a Cisco 10GBASE-LR or -SR transceiver and cable, insert the transceiver into a downlink optical port on a leaf switch before connecting the cable to the transceiver.
  • Page 41: Connecting Leaf Switches To Spine Switches

    You cannot include NX-OS line cards in the same chassis when running in ACI mode. Note Multiple uplinks from a leaf switch to a spine switch is supported. A symmetrical topology is recommended so that all devices have equal access to resources. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 42: Installing A Gigabit Ethernet Module (Gem)

    Migration of Nodes From a First Generation Switch to a Second Generation Switch You have first generation Cisco Nexus 9000 series switches that may or may not be comprising a virtual port channel (vPC). You are migrating to second generation Cisco Nexus 9000 series switches using the same cables.
  • Page 43 Before you begin • Move any Cisco Application Policy Infrastructure Controllers (APICs) that are connected to the first generation switches that you are migrating to any other switches in the fabric and wait for the Cisco APIC cluster to become "Fully Fit."...
  • Page 44: Setting Up An Optional Console Interface

    Register the new second generation switch with the Cisco APIC. Register the new node with the same node name and node ID. This switch becomes part of the fabric. The Cisco APIC pushes the policies to the new switch and keeps down the vPC legs because there is a mismatch of the generation of switches.
  • Page 45: Setting Up An Optional Management Connection

    DB-9 connector on the other end of the cable to the serial port on the console device. What to do next You can now perform the initial configuration for the switch (see the Cisco ACI Getting Started Guide). Setting Up an Optional Management Connection You can optionally set up an out-of-band management connection for monitoring and troubleshooting purposes.
  • Page 46 Use the narrow end of the optics extraction tool to carefully remove the transceiver module (see the following image). Step 4 Place the transceiver module in an antistatic bag or other protective environment. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 47: Maintaining Transceivers And Optical Cables

    • Inspect routinely for dust and damage. If you suspect damage, clean and then inspect fiber ends under a microscope to determine if damage has occurred. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 48 Connecting the Switch to the ACI Fabric Maintaining Transceivers and Optical Cables Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 49: Replacing Components

    Hold the module by its handle and do not touch the electrical connectors on its backside. Also, to protect the electrical connectors, avoid letting them come in contact with anything other than the electrical connectors inside the chassis. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 50: Replacing A Power Supply Module

    If the STS LED does not turn on, slide the module out of the chassis, and visually check the electrical connectors on the back side of the chassis for damage. If damaged, contact Cisco Technical Assistance for help. If undamaged, repeat the previous step to reinstall the module.
  • Page 51: Removing An Hvac/Hvdc Power Supply

    Be sure that the LEDs turn off on the power supply that you are removing. Step 2 Remove the power cable from the power supply by doing the following: Step 3 Grasp the power supply handle while pressing the release latch towards the power supply handle. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 52: Installing An Ac Power Supply

    Make sure that the other end of the power cable is attached to the appropriate power source for the power supply. Note Depending on the outlet receptacle on your power distribution unit, you might need the optional jumper cable to connect the switch to your outlet receptacle. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 53: Installing An Hvac/Hvdc Power Supply

    Verify that the power supply is operational by making sure that the power supply LED is green. Installing a DC Power Supply You can replace one power supply while the other one provides power to the switch. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 54: Connecting A Power Cable To An Nxa-Pdc-930W Power Supply

    The recommended wire gauge is 8 AWG. The minimum wire gauge is 10 AWG. Warning Statement 342 Before Connecting to System Power Supply High touch/leakage current – Permanently connected protective earth ground is essential before connecting to system power supply. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 55 Verify that the other ends of the cables are attached to the DC power source and ground. Step 5 Turn on the circuit breaker Step 6 You are now ready to turn on the DC power source. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 56 Replacing Components Connecting a Power Cable to an NXA-PDC-930W Power Supply Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 57: Rack Specifications

    • Standard 19-inch (48.3 cm) (two- or four-post EIA cabinet or rack, with mounting rails that conform to English universal hole spacing per section 1 of ANSI/EIA-310-D-1992). For more information, see Requirements Specific to Perforated Cabinets, on page Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 58: Requirements Specific To Standard Open Racks

    • The roof should be perforated with at least a 20 percent open area. • The cabinet floor should be open or perforated to enhance cooling. The Cisco R Series rack conforms to these requirements. Cable Management Guidelines To help with cable management, you might want to allow additional space in the rack above and below the chassis to make it easier to route all of the fiber optic or copper cables through the rack.
  • Page 59: System Specifications

    Ambient operating temperature 32 to 104°F (0 to 40°C) Ambient nonoperating –40 to 158°F (–40 to 70°C) Relative Nonoperating 5 to 95% humidity Altitude Operating 0 to 13,123 feet (0 to 4,000 meters) Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 60: Switch Dimensions

    Some power supplies have capabilities that are greater than the maximum power requirements for a switch. To determine the power consumption characteristics for the switch, use the typical and maximum requirements that are listed in the following table. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 61: Power Specifications

    Input voltage Nominal (Range) • AC (for 1230 W output) • 200 to 277 VAC • DC (for 1230 W output) AC input frequency Nominal: 50 to 60 Hz (Range: 47-63 Hz) Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 62: 930-W Dc Power Supply Specifications

    35 A (sub-cycle duration) Maximum hold-up time 8 ms at 930 W Power supply output voltage 12 VDC Power supply standby voltage 12 VDC Efficiency rating Greater than 92% at 50% load Form factor RSP1 Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 63: Power Cable Specifications

    250 V, 10 A, 8.2 feet (2.5 m) Switzerland CAB-9K10A-SW 250 VAC, 10 A, MP232 plug, 8.2 feet (2.5 m) United Kingdom CAB-9K10A-UK 250 VAC, 10 A, BS1363 plug (13 A fuse), 8.2 (2.5 Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 64: Hvac/Hvdc Power Cables Supported By Aci-Mode And Nx-Os Mode Switches

    (+200/-200 V DC) NO-POWER-CORD All except Argentina, Not applicable Brazil, and Japan No power cord included with switch Table 1: HVAC/HVDC Power Cables Callout Table Connect this end to the power supply unit. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 65: Dc Power Cable Specifications

    Products should comply with CE Markings according to directives 2004/108/EC and 2006/95/EC. Safety • CAN/CSA-C22.2 No. 60950-1 Second Edition • EN 60950-1 Second Edition • IEC 60950-1 Second Edition • IEC 623681 • AS/NZS 60950-1 • GB4943 Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 66 • CNS13438 Class A EMC: Immunity • EN55024 • CISPR24 • EN300386 • KN 61000-4 series RoHS The product is RoH-6 compliant with exceptions for leaded-ball grid-array (BGA) balls and lead press-fit connectors. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 67: Leds

    Power supply is on and outputting power to the switch. Flashing Power supply is connected to an AC power source but not outputting power green to the switch. The power supply may not be properly installed in the chassis. Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 68 Power supply is installed without a connection to a power source. (10 seconds) then amber Amber Power supply failure—possibly one of the following conditions: • Over voltage • Over current • Over temperature • Power supply fan failure Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 69: Additional Kits

    • Front-mount brackets (2) Vent Bracket The following table lists and illustrates the vent bracket (NXA-ACC-BAV4). Note You require the vent bracket (NXA-ACC-BAV4) for NEBS (Network Equipment-Building System) compliance only. Illustration Description Quantity Vent bracket Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...
  • Page 70 Additional Kits Vent Bracket Cisco Nexus 93360YC-FX2 ACI-Mode Switch Hardware Installation Guide...