Trane Precedent DSJ150A Installation, Operation And Maintenance Manual page 22

Table of Contents

Advertisement

Installation
uniform lift. The minimum distance between the lifting
hook and the top of the unit should be 7 feet.
5. Test-lift the unit to ensure it is properly rigged and
balanced, make any necessary rigging adjustments.
Figure 16. Fork pockets — 12.5 to 25 ton standard
efficiency units
REMOVE SIX
FORK LIFT BRACKETS
REMOVE TWO
SHIPPING PROTECTIONS
6. Lift the unit enough to allow the removal of base fork
pocket protection components as shown in the
following figures.
7. Downflow units; align the base rail of the unit with the
curb rail while lowering the unit onto the curb. Make
sure that the gasket on the curb is not damaged while
positioning the unit.
General Unit Requirements
The checklist listed below is a summary of the steps
required to successfully install a commercial unit. This
checklist is intended to acquaint the installing personnel
with what is required in the installation process. It does not
replace the detailed instructions called out in the applicable
sections of this manual.
Check the unit for shipping damage and material
shortage; file a freight claim and notify appropriate
sales representative.
Verify correct model, options and voltage from unit
nameplate.
Verify that the installation location of the unit will
provide the required clearance for proper operation.
Assemble and install the roof curb (if applicable). Refer
to the latest edition of the curb installers guide that
ships with each curb kit.
Fabricate and install ductwork; secure ductwork to
curb.
Install pitch pocket for power supply through building
roof. (If applicable)
Rigging the unit.
Set the unit onto the curb; check for levelness.
Ensure unit-to-curb seal is tight and without buckles or
cracks.
22
REMOVE WOODEN BOARDS
Install and connect a condensate drain line to the
evaporator drain connection.
Factory Installed Economizer
Ensure the economizer has been pulled out into the
operating position. Refer to the economizer installers
guide for proper position and setup.
Install all access panels.
External Vent Hood Installation
Note: This procedure applies only to 12.5 to 25 tons dual
fuel (gas heat) models only.
1. Remove and discard the cover plate located on the gas
heat panel.
Important:
Make sure you read the label located on
the cover plate before you discard it.
Do not discard the fastening screws! They
will be needed to install the vent hood.
Figure 17. Discard cover plate
2. Locate the vent hood behind the panel, on the right side
of the burner assembly.
PKGP-SVX010B-EN

Advertisement

Table of Contents
loading

This manual is also suitable for:

Precedent wsj300aPrecedent wsj150aPrecedent dsj300a

Table of Contents