ASSEMBLY AFTER A COMPLETE TEAR DOWN
If the unit has been torn down completely, the
following summary identifies the assembly pro-
cedures necessary to completely assemble the
unit. Each assembly procedure is located by a
page reference.
The part reference numbers provided in each
assembly procedure are keyed to the individual
exploded views, and are also keyed to the
complete unit exploded views on pages and 45.
1. Install the axle shaft. See page 39.
2. Install the hydraulic components. See pages
33-38.
3. Install the bypass rod and arm. See page
32.
4. Install the input shaft. See page 31.
5. Install the charge pump. See page 29.
6. Install the reduction gears, pinion gear and
bull gear. See page 27.
ZT-2800
/ZT-3100
/ZT-3200
®
®
Sealant Path for Center Section
Figure 38, Sealant Application Diagram
TM
7. Apply sealant to the main housing and cen-
ter section prior to installing the side cover.
See diagram below.
NOTE: Prior to applying the new sealant, the
old sealant must be removed from all
surfaces.
A small consistent bead (approx.
1/16 – 1/8 inch) of the sealant around
the housing face will be sufficient. Use
sparingly.
The illustration below indicates the cor-
rect sealant path.
8. Install the RTN assembly. See page 14.
9. Install the transaxle onto the vehicle.
10. Install new oil filter and fill the transaxle with
new oil. See pages 10 and 11.
11. Perform the purge procedures listed on
page 12.
Sealant Path for Main Housing