Assembly After Complete Tear Down - Hydro-Gear ZT-2800 Service And Repair Manual

Integrated zero-turn transaxle
Hide thumbs Also See for ZT-2800:
Table of Contents

Advertisement

asseMBLY afTer a COMpLeTe Tear dOwn
If the unit has been torn down completely, the
following summary identifies the assembly pro-
cedures necessary to completely assemble the
unit. Each assembly procedure is located by a
page reference.
The part reference numbers provided in each
assembly procedure are keyed to the indi-
vidual exploded views, and are also keyed to
the complete unit exploded views on pages 42
and 44.
1. Install the axle shaft. See pages 36 or 37..
2. Install the hydraulic components. See pages
30-35.
3. Install the bypass rod and arm. See page
29.
4. Install the input shaft. See page 28.
5. Install the charge pump. See page 27.
6. Install the reduction gears, pinion gear and
bull gear. See page 26.
38
Sealant Path for Center Section
figure 35, sealant application diagram
7. Apply sealant to the main housing and cen-
ter section prior to installing the side cover.
See page 25 and diagram below.
NOTE: Prior to applying the new sealant, the
old sealant must be removed from all
surfaces.
A small consistent bead (approx.
1/16 – 1/8 inch) of the sealant around
the housing face will be sufficient. Use
sparingly.
The illustration below indicates the cor-
rect sealant path.
8. Install the RTN assembly. See page 14.
9. Install the transaxle onto the vehicle.
10. Install new oil filter and fill the transaxle with
new oil. See pages 9 and 10.
11. Perform the purge procedures listed on
page 12.
Sealant Path for Main Housing
ZT-2800
/ZT-3100™/ZT-3400™
®

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Zt-3100Zt-3400

Table of Contents