01
Installing the Cabinet
1. Before installation, read the user manual carefully to get familiar with product information and safety precautions.
2. Use insulated tools when installing the equipment.
3. Only engineers certified by Huawei or its agent are allowed to install, commission, and maintain the UPS. Otherwise,
personal injury or equipment damage may occur, and the resulting UPS faults are beyond the warranty scope.
4. This document describes the installation procedure for a single UPS. For details about how to install a parallel system,
contact Huawei technical support.
Model
Weight
UPS5000-H-200K-NTJ
< 850 kg
Copper Bar Layout and Specifications (unit: mm)
Bypass input
PE
Battery
Mains input
Item
50 kVA
100 kVA 150 kVA
Mains input current (A)
184
368
R1
100
2 x 100
Mains input
Recommended cross-
S1
100
2 x 100
sectional area (mm
2
)
T1
100
2 x 100
PE
38
2 x 38
Bypass input current (A)
144
289
R2
100
2 x 100
Bypass input
S2
100
2 x 100
Recommended cross-
sectional area (mm
2
)
T2
100
2 x 100
PE
38
2 x 38
Output current (A)
144
289
U
100
2 x 100
Output
Recommended cross-
V
100
2 x 100
sectional area (mm
2
)
W
100
2 x 100
PE
38
2 x 38
Nominal battery discharge
225
450
current (A)
Maximum battery discharge
Battery input
270
539
current (A)
(lead-acid
+
2 x 100
2 x 200
battery)
Recommended cross-
-
2 x 100
2 x 200
sectional area (mm
2
)
PE
2 x 38
2 x 100
Nominal battery discharge
104
208
current (A)
Battery input
Maximum battery discharge
130
261
(SmartLi)
current (A)
Recommended cross-sectional
For details, see the IEC-60364-5-52
area
specifications and
Equipotential
Recommended cross-sectional
16
ground point
area (mm
2
)
UPS5000-H-200K-NTJ Quick Guide
Dimensions (H x W x D)
2000 mm x 600 mm x 1000 mm
Space
Planning
Output
200 kVA Remarks
553
737
2 x 200
2 x 250
2 x 200
2 x 250
2 x 200
2 x 250
2 x 100
2 x 150
433
577
2 x 200
2 x 250
2 x 200
2 x 250
2 x 200
2 x 250
Connection method:
2 x 100
2 x 150
Crimped DT terminal
433
577
Bolt Specifications:
2 x 200
2 x 250
R/S/T/U/V/W/+/-:
2 x 200
2 x 250
M16 x 55 mm (120 N· m)
2 x 200
2 x 250
PE: M12 x 30 mm (47 N· m)
2 x 100
2 x 150
Equipotential ground point:
676
901
M6 x 20 mm (4.5 N· m)
NOTE:
809
1079
The currents listed in the
3 x 200
4 x 200
table are measured at a rated
3 x 200
4 x 200
voltage of 200 V. For other
2 x 150
2 x 200
data, see the user manual.
312
416
391
521
SmartLi User Manual
.
Unpacking
Securing the Cabinet
Installation Not Against a Wall
M12 bolt
Spring washer
Flat washer
Expansion sleeve
unit: mm
Expansion nut
1
Issue: 02
Date: 2022-06-20
Installing Lifting Eyes
•
When hoisting the
UPS, install lifting
eyes on the top of
the cabinet.
•
Store the removed
screws. Reinstall
them after hoisting
the cabinet.
Iron bar
Lifting eye
Concrete floor
Without Antiseismic Requirements
With Antiseismic Requirements
Copyright © Huawei Technologies Co., Ltd. 2022. All rights reserved.
Use iron bars with a diameter not
•
greater than 20 mm to install
lifting eyes.
For safety, the lifting ropes for
•
hoisting a cabinet should be able
to withstand a weight that is more
than three times the maximum
weight of the cabinet.