Vacuum Drying And Leakage Checking - Fisher FSAIF-CP-91AE3 Technical Manual

Split wall-mounted type
Table of Contents

Advertisement

Outer diameter of pipe
(inch(mm))
1/4" (6.35)
3/8" (9.52)
1/2" (12.7)
5/8" (15.9)
3/4" (19)
After flared the pipe, the opening part must be seal
by end cover or adhesive tape to avoid duct or exog-
enous impurity come into the pipe.
7. Drill holes if the pipes need to pass the wall.
8. According to the field condition to bend the pipes so
that it can pass the wall smoothly.
9. Bind and wrap the wire together with the insulated pipe
if necessary.
10. Set the wall conduit
11. Set the supporter for the pipe.
12. Locate the pipe and fix it by supporter
For horizontal refrigerant pipe, the distance be-
tween supporters should not be exceed 1m.
For vertical refrigerant pipe, the distance between
supporters should not be exceed 1.5m.
13. Connect the pipe to indoor unit and outdoor unit by
using two spanners.
Be sure to use two spanners and proper torque to
fasten the nut, too large torque will damage the
bellmouthing, and too small torque may cause
leakage. Refer the following table for different pipe
connection.
Pipe Diameter
N.
1/4" (6.35)
(11~11.8)
3/8" (9.52)
(18.4~19.18)
1/2" (12.7)
(25.8~26.55)
5/8" (15.9)
(33.19~34.67)
3/4" (19)
(47.94~49.42)
Page 52
A (mm/inch)
Min
Max
1.3/0.05
0.7/0.0275
1.0/0.04
1.6/0.063
1.8/0.07
1.0/0.04
2.0/0.078
2.2/0.086
2.0/0.078
2.4/0.094
Torque
Sketch map
m(lb.ft)
15~16
25~26
35~36
45~47
65~67
6. Vacuum Drying and Leakage
Checking
6.1
Purpose of vacuum drying
Eliminating moisture in system to prevent the phe-
nomena of ice-blockage and copper oxidation.
Ice-blockage shall cause abnormal operation of
system, while copper oxide shall damage
compressor.
Eliminating the non-condensable gas (air) in system
to prevent the components oxidizing, pressure fluc-
tuation and bad heat exchange during the operation
of system.
6.2
Selection of vacuum pump
The ultimate vacuum degree of vacuum pump shall
be -756mmHg or above.
Precision of vacuum pump shall reach 0.02mmHg or
above.
6.3
Operation procedure for vacuum
drying
Due to different construction environment, two kinds of
vacuum drying ways could be chosen, namely ordinary
vacuum drying and special vacuum drying.
6.3.1
Ordinary vacuum drying
1. When conduct first vacuum drying, connect pressure
gauge to the infusing mouth of gas pipe and liquid pipe,
and keep vacuum pump running for 1hour (vacuum
degree of vacuum pump shall be reached -755mmHg).
2. If the vacuum degree of vacuum pump could not reach
-755mmHg after 1 hour of drying, it indicates that there is
moisture or leakage in pipeline system and need to go on
with drying for half an hour.
3. If the vacuum degree of vacuum pump still could not
reach -755mmHg after 1.5 hours of drying, check whether
there is leakage source.
4 . Leakage test: After the vacuum degree reaches
-755mmHg, stop vacuum drying and keep the pressure for
1 hour. If the indicator of vacuum gauge does not go up,
it is qualified. If going up, it indicates that there is moisture
or leak source.
6.3.2
Special vacuum drying
The special vacuum drying method shall be adopted when:
1. Finding moisture during flushing refrigerant pipe.
2. Conducting construction on rainy day, because rain