FusionModule1000A40 Prefabricated All-in-One
Data Center
Installation Guide
Figure 9-24 Cable interconnection position
Step 7 Install the electromagnetic valve.
Do not install the electromagnetic valve when installing the fire extinguisher cylinder for the
first time. Install the electromagnetic valve when commissioning the fire extinguishing system.
1.
----End
Issue 07 (2022-12-15)
NO TE
Remove the protective cover at the electromagnetic valve installation position
on the container valve. Align the electromagnetic valve and the container
valve, and tighten the electromagnetic valve clockwise.
Figure 9-25 Removing the electromagnetic valve protective cover
Copyright © Huawei Digital Power Technologies Co., Ltd.
9 Installing Devices Inside Pre-fab. Modules
94