QUICK START GUIDE
Step 9 - Connect GMT Style Fuse Loads- skip if not present
6.
Reposition the Tie Bar to the bottom of the panel if desired - 2 screws.
7.
Secure wires to Tie Bar.
Step 10 - Label Connections
1.
Mark each connected circuit identification on the ID label.
2.
Snap the ID Label onto the Tie Bar.
Step 11 - Install Breakers and Fuses
Install breakers and fuses into positions as specified in Site Engineering Instructions.
Bullet Breakers
CAUTION:
1.
Install breakers oriented as shown Orientation is different for Left and Right breakers.
2.
Install proper breaker type in Battery and Load positions.
Battery Breakers (Yellow handle) in Battery Position. (Right positions only)
Load Breakers (Black handle) in Load Positions. (Right and Left positions)
1.
Remove Retention Cover (2 screws)
2.
Verify that each Breaker is OFF.
3.
Insert each Breaker fully into its position — oriented as shown below.