12 Commissioning
In this chapter
12.1 Overview: Commissioning
12.2 Precautions when commissioning
2MXM-A9, 3MXM-A9, 4MXM-A9, 5MXM-A9
R32 Split series
4P600463-7G – 2022.09
NOTICE
General commissioning checklist. Next to the commissioning instructions in this
chapter, a general commissioning checklist is also available on the Daikin Business
Portal (authentication required).
The general commissioning checklist is complementary to the instructions in this
chapter and can be used as a guideline and reporting template during commissioning
and hand-over to the user.
12.1
Overview: Commissioning ......................................................................................................................................................
12.2
Precautions when commissioning..........................................................................................................................................
12.3
Checklist before commissioning.............................................................................................................................................
12.4
Checklist during commissioning .............................................................................................................................................
12.5
Trial operation and testing .....................................................................................................................................................
12.5.1
About wiring error check .......................................................................................................................................
12.5.2
To perform a test run.............................................................................................................................................
12.6
Starting up the outdoor unit ..................................................................................................................................................
This chapter describes what you have to do and know to commission the system
after it is installed.
Typical workflow
Commissioning typically consists of the following stages:
1
Checking the "Checklist before commissioning".
2
Performing a test run for the system.
DANGER: RISK OF ELECTROCUTION
DANGER: RISK OF BURNING/SCALDING
CAUTION
Do NOT perform the test operation while working on the indoor units.
When performing the test operation, NOT ONLY the outdoor unit, but the connected
indoor unit will operate as well. Working on an indoor unit while performing a test
operation is dangerous.
CAUTION
Do NOT insert fingers, rods or other objects into the air inlet or outlet. Do NOT
remove the fan guard. When the fan is rotating at high speed, it will cause injury.
12
Commissioning
|
Installer reference guide
61
61
61
62
62
63
63
64
65
Need help?
Do you have a question about the 3MXM40A2V1B9 and is the answer not in the manual?
Questions and answers