(2) After piping is finished, check if the drain flows
smoothly.
[When the electric wiring work is finished]
• Gradually pour 1/4 gal. (1 ) of water from the filling port
at the bottom of the drain socket or the discharge into
the drain pan, and be careful spraying water to the
electric components such as drain pump and confirm
drainage by operating the indoor unit under cooling
mode according to 10. FIELD SETTING. (Refer to
Fig. 18)
Control box
Drain socket
Filling port
Drain pan
Discharge
Inspection
Drain socket
window
(With rubber cap)
Plastic container
for pouring water
[Method of adding water]
Fig. 18
[When the electric wiring work is not finished]
• The electric wiring works (including grounding) must
be carried out by a qualified electrician.
• If a qualified person is not present, after the electric
wiring work is finished, check the drainage accord ing
to the method specified in [When the electric wiring
work is finished].
1. Open the control box cover and connect the single
phase 208/230 V power supply to the terminal (L1,
L2) on the terminal block (X1M).
Connect the ground wiring to the ground terminal.
2. Make sure the control box cover is closed before
turning on the power supply.
• Throughout the whole process, carry out the
work giving caution to the wiring around the con-
trol box so that the connectors may not come off.
3. Gradually pour 1/4 gal. (1 ) of water from the dis-
charge into the drain pan, and be careful spraying
water to the electric components such as drain
pump. (Refer to Fig. 18)
4. When the power supply is turned on, the drain pump
will operate. Drainage can be checked at the trans-
parent part of the drain socket.
(The drain pump will automatically stop after 10
minutes.)
The drainage of water can be confirmed with water
level change in the drain pan through the access
window.
• Do not connect the drain piping directly to the
sewage that gives off ammonia odor.
The ammonia in the sewage may go through the
drain piping and corrode the heat exchanger of
the indoor unit.
English
(3) Sweating may occur and result in water leakage.
Control box cover
Terminal block
for wiring between
the indoor and
outdoor units
Screw
Drain pump
position
• Do not apply external force to the float switch. (It
may result in malfunction)
• Do not touch the drain pump.
Touching the drain pump may cause electric shock.
5. Turn off the power supply after checking drainage,
and remove the power supply wiring.
6. Attach the control box cover as before.
Therefore, make sure to insulate the following 2
locations (drain piping that laid indoors and drain
sockets).
• Use the provided sealing material (Large) (6), and
perform the thermal insulation of the metal clamp (1)
and drain hose (2) after checking the drainage of water.
(Refer to Fig. 19)
Sealing material - Large
(6) (Accessory)
No clearance is
allowed.
Sealing material (Large) (6)
Drain hose (2)
(Accessory)
(Accessory)
Start wrapping from where the
metal clamp (1) is tightened.
Metal clamp (1)
(Accessory)
Wrap the sealing material (Large) (6)
so that the metal clamp (1) end side
may be doubled.
Fig. 19