Pre-Start-Up/Start-Up; Start-Up, General; Unit Preparation; Additional Installation/Inspection - Carrier WeatherMaker 50TC 17-30 Series Service And Maintenance Instructions

Single package rooftop unit with electric cooling and optional electric heat with puron (r-410a) refrigerant
Table of Contents

Advertisement

If one or more alarms are present and there has been no keypad ac-
tivity for at least 5 minutes, the Alarms menu displays and cycles
through the active alarms.
You can also navigate to the Alarms menu at any time.
Clearing Alarms
Once the alarm has been identified and the cause has been re-
moved (e.g. replaced faulty sensor) the alarm can be cleared from
the display.
To clear an alarm, perform the following:
1. Navigate to the desired alarm.
2. Press the
(Enter) button. ERASE? displays.
3. Press the
(Enter) button. ALARM ERASED displays.
4. Press the
(Menu up/Exit) button to complete the
action and return to the previous menu.
If the alarm still exists after clearing it, it is redisplayed within
5 seconds.

PRE-START-UP/START-UP

WARNING
PERSONAL INJURY HAZARD
Failure to follow this warning could result in personal injury or
death.
1.
Follow recognized safety practices and wear approved
Personal Protective Equipment (PPE), including safety
glasses and gloves when checking or servicing refrigerant
system.
2.
Do not use a torch to remove any component. System
contains oil and refrigerant under pressure. To remove a
component, wear PPE and proceed as follows:
a. Shut off all electrical power to unit. Apply applicable
lockout/tag-out procedures.
b. Recover refrigerant to relieve all pressure from sys-
tem using both high-pressure and low pressure ports.
c. Do not use a torch. Cut component connection tubing
with tubing cutter and remove component from unit.
d. Carefully un-sweat remaining tubing stubs when
necessary. Oil can ignite when exposed to torch
flame.
3.
Do not operate compressor or provide any electric power
to unit unless compressor terminal cover is in place and
secured.
4.
Do not remove compressor terminal cover until all electri-
cal power is disconnected and approved lockout/tag-out
procedures are in place.
5.
Relieve all pressure from system before touching or dis-
turbing anything inside terminal box whenever refriger-
ant leak is suspected around compressor terminals.
6.
Never attempt to repair a soldered connection while
refrigerant system is under pressure.
WARNING
ELECTRICAL OPERATION HAZARD
Failure to follow this warning could result in personal injury or
death.
The unit must be electrically grounded in accordance with
local codes and NEC ANSI/NFPA 70 (American National
Standards Institute/National Fire Protection Association).
Proceed as follows to inspect and prepare the unit for initial start-
up:
1.
Remove all access panels.
2.
Read and follow instructions on all WARNING, CAUTION,
and INFORMATION labels attached to, or shipped with,
unit.
3.
Make the following inspections:
a. Inspect for shipping and handling damages such as bro-
ken lines, loose parts, or disconnected wires, etc.
b. Inspect for oil at all refrigerant tubing connections and
on unit base. Detecting oil generally indicates a refriger-
ant leak. Leak-test all refrigerant tubing connections
using electronic leak detector, halide torch, or liquid-
soap solution.
c. Inspect all field-wiring and factory-wiring connections.
Be sure that connections are completed and tight. Be
sure that wires are not in contact with refrigerant tubing
or sharp edges.
d. Inspect coil fins. If damaged during shipping and han-
dling, carefully straighten fins with a fin comb.
4.
Verify the following conditions:
a. Make sure that condenser-fan blade are correctly posi-
tioned in fan orifice. See Condenser-Fan Adjustment
section for more details.
b. Make sure that air filter(s) is in place.
c. Make sure that condensate drain trap is filled with water
to ensure proper drainage.
d. Make sure that all tools and miscellaneous loose parts
have been removed.

START-UP, GENERAL

Unit Preparation

Make sure that unit has been installed in accordance with installa-
tion instructions and applicable codes.
IMPORTANT: Follow the base unit's start-up sequence as de-
scribed in the unit's installation instructions.
In addition to the base unit start-up, there are a few steps needed to
properly start-up the controls. RTU-OPEN's Service Test function
should be used to assist in the base unit start-up and also allows
verification of output operation. Controller configuration is also
part of start-up. This is especially important when field accessories
have been added to the unit. The factory pre-configures options in-
stalled at the factory. There may also be additional installation
steps or inspection required during the start-up process.

Additional Installation/Inspection

Inspect the field installed accessories for proper installation, mak-
ing note of which ones do or do not require configuration changes.
Inspect the RTU-OPEN's Alarms for initial insight to any poten-
tial issues. Refer to the following manual: "Controls, Start-up, Op-
eration and Troubleshooting Instructions." Inspect the SAT sensor
for relocation as intended during installation. Inspect special wir-
ing as directed.

Return-Air Filters

Ensure correct filters are installed in unit (see Appendix B - Physi-
cal Data). Do not operate unit without return-air filters.

Outdoor-Air Inlet Screens

Outdoor-air inlet screen must be in place before operating unit.
56

Advertisement

Table of Contents
loading

Table of Contents