Vivreau V3-204 Commissioning Instructions

Vivreau V3-204 Commissioning Instructions

Bottling system
Hide thumbs Also See for V3-204:

Advertisement

Quick Links

Confirm that the proper services are available. The water supply must be a ½" water line with
a ½" threaded ball valve female end. Anything smaller than ½" is not acceptable and should
never be used. The electrical outlet must be within the range of the power cord of the
machine, extension cords should never be used. CO 2 is also provided by the customer in
either a tank or with a line from a bulk or remote system. If connecting to an existing system
the customer must provide a ¼" barbed shutoff within 40" of the installation.
If any of the required services are missing/incorrect or if you have any questions regarding
the commissioning instructions, please call 877-999-1044 option #5, and someone from our
Tech Support Team will provide further instructions.
Open equipment packaging and inspect for damage. Make sure the legs are level, adjust if
necessary. If anything is damaged or missing call the Vivreau service number and report the
missing or damaged parts.
Locate the installation instructions and checklist, confirm all parts are included using the
installation parts diagram included with the paperwork.
Make the connections at the customer water supply, check valve and filter head, but do not
connect to the back of the machine yet. The filter head can be mounted on a wall or onto the
back of the machine.
Remove the rear water bath access plug. Place the drip tray upside down on the counter to
prop up the front legs. Slowly fill the water bath using the water supply line. Once full level
the machine and replace the plug.
Connect the water supply to the back of the machine and secure with a red clip.
Connect the CO 2 tank or the customer supplied CO 2 line to the provided CO 2 regulator and
set pressure as per instructions. If connecting to bulk CO 2 or an existing system make sure
the customer has provided the CO 2 line with the ¼" barbed shutoff. The general setting for
CO 2 is between 65 and 70 PSI. Connect the regulator to the rear of the machine and secure
with a red clip.
vivreauwater.com
Tel: 877-999-1044 (Option #5 for Tech Support)
V3-204
VIVREAU BOTTLING SYSTEM
COMMISSIONING INSTRUCTIONS

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the V3-204 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Vivreau V3-204

  • Page 1 Tech Support Team will provide further instructions. Open equipment packaging and inspect for damage. Make sure the legs are level, adjust if necessary. If anything is damaged or missing call the Vivreau service number and report the missing or damaged parts.
  • Page 2 Before putting the system into service taste test both still and sparkling water. The “Do not use” sign can now be removed. Make sure to completely fill out the Vivreau Installation Checklist recording all information needed, including the serial number and accurate system location.