The ASCO 7000 Series Automatic Transfer & Bypass–
Isolation Switch (ATB) consists of an upper bypass–isola-
tion switch, a transfer switch, a monitoring and transfer
controller, and door–mounted controls. The ATB is
factory wired and tested. Installation requires removal of
the shipping skid then securing the enclosure to the
supporting foundation.
Remove the Transfer Switch
The Transfer Switch is shipped inside the enclosure (ATS
side) in the fully engaged position. Before installing the
enclosure remove the Transfer Switch as follows:
1. Open the enclosure doors and install the two ramps
(stored on right side).
2. Remove the Isolation Handle which is stored on the
lower right front of the Transfer Switch carriage
frame. Install the Isolation Handle onto the
protruding shaft and turn it counterclockwise
(approximately 10 turns) until it stops.
3. Unplug J2 and J5 harness plugs, and roll out the
Transfer Switch. Cover it to keep it clean.
Supporting Foundation
The supporting foundation and adjacent area must be
level and straight, otherwise the Transfer Switch and
enclosure may not align causing door problems. The
floor under the enclosure must be flat and level. This is
very important! The structure of the enclosure must be
straight and square. Allow at least 36 inches for roll out of
Transfer Switch. Refer to the enclosure drawing for
required door opening space.
If bottom cable entry is used, the foundation must be pre-
pared so that conduit stubs are located correctly. Refer to
appropriate enclosure outline drawing for specified cable
entrance area and location. Provide cable bending space
and clearance to live metal parts. When a concrete floor is
poured, use interlocking conduit spacer caps or a wood or
metal template to maintain proper conduit alignment.
SECTION 1

INSTALLATION

Refer to the enclosure outline drawing furnished with
this switch and mount the 7000 Series ATB according to
the details and instructions shown on the drawing.
Bolt the cubicle sections together so that they are lined up
on the front faces. See Figure 1–1.
Do not connect the power conductors to the ATB until
they are tested. Installing power cables in conduit, cable
troughs, and ceiling-suspended hangers often requires
considerable force. The pulling of cables can damage
insulation and stretch or break the conductor's strands.
For this reason, after the cables are pulled into position,
and before they are connected they should be tested to
verify that they are not defective or have been damaged
during installation.
1--1
Mounting
De–energize the conductors before making any
line or auxiliary circuitry connections. Be sure
that Normal and Emergency line connections
are in proper phase rotation. Place engine gen-
erator starting control in the OFF position. Make
sure engine generator is not in operation.

Testing Power Conductors

!
Protect the switch from construction grit
and metal chips to prevent malfunction or
shortened life for the ATB switch.